Common Data Centre Maintenance Mistakes and How to Avoid Them Malaysia

Data-centre maintenance mistakes do not always cause an immediate shutdown.

Some mistakes gradually create poor airflow, hidden electrical hotspots, unreliable cable records and incomplete maintenance evidence.

Understanding the most common data centre maintenance mistakes helps Malaysian facility teams improve inspections across server rooms, UPS systems, switchgear, network racks and cooling equipment.

1. Relying on One Room Temperature Sensor

A single wall-mounted sensor may not detect:

  • Hotspots at the top of a rack

  • Warm air behind equipment

  • High temperature near a UPS

  • Poor cooling inside a battery area

  • One overloaded network rack

Better Approach

Measure temperature at:

  • Rack front

  • Rack rear

  • Top, middle and bottom

  • Hot aisle

  • Cold aisle

  • Cooling-unit intake and outlet

Use a data logger when conditions must be recorded over time.

2. Checking Temperature Only During Office Hours

A server room may overheat at night when:

  • Cooling settings change

  • Building HVAC reduces operation

  • A cooling unit cycles

  • Equipment load increases

  • Fewer personnel are present to notice alarms

Better Approach

Use an Elitech RC-5 Temperature Data Logger or a suitable temperature-and-humidity logger such as the Elitech GSP-6 Pro to record conditions overnight and during weekends.

3. Placing the Data Logger in the Wrong Location

A logger directly in cold supply air may show an unrealistically low reading.

A logger against a hot server may record equipment heat rather than representative air temperature.

Better Approach

Define the monitoring objective and document:

  • Exact location

  • Rack number

  • Front or rear

  • Height

  • Distance from equipment

  • Nearby cooling outlet

  • Recording interval

4. Reviewing Only Maximum and Minimum Logger Readings

Maximum and minimum values do not show:

  • Alarm duration

  • Repeated cooling cycles

  • Time of the event

  • Gradual temperature rise

  • Differences between day and night

Better Approach

Review the complete graph and compare it with cooling-system operation, server load and maintenance events.

5. Assuming the Air Conditioner Is Effective Because It Is Running

A cooling unit may operate while delivering insufficient airflow because of:

  • Dirty filter

  • Damaged fan

  • Closed damper

  • Blocked outlet

  • Low underfloor pressure

  • Air leakage

  • Control problem

Better Approach

Measure:

  • Intake and outlet temperature

  • Air velocity

  • Differential pressure

  • Rack inlet temperature

6. Measuring Airflow at Only One Point

Air velocity may vary significantly across a large grille or floor tile.

Better Approach

Take several readings at consistent positions and record the average where appropriate.

7. Ignoring Differential Pressure

A room or raised-floor system may have reasonable temperature but incorrect pressure relationships.

This can contribute to:

  • Weak floor-tile airflow

  • Dust entry

  • Hot and cold air mixing

  • Containment leakage

  • Incorrect airflow direction

Better Approach

Use a differential pressure meter between clearly identified test points.

8. Performing Thermal Inspection Without Recording Electrical Load

Electrical temperature changes with current.

A circuit inspected at low load may not show the hotspot that appears during normal operation.

Better Approach

Record:

  • Equipment load

  • Phase current

  • UPS load percentage

  • Ambient temperature

  • Operating mode

  • Inspection time

9. Treating Every Warm Component as Faulty

Some components naturally operate warmer than others.

Better Approach

Compare:

  • Similar phases

  • Similar breakers

  • Identical servers

  • Parallel UPS modules

  • Current and previous thermal images

The temperature pattern and difference are often more informative than one isolated value.

10. Using an Infrared Thermometer to Search for an Unknown Hotspot

An infrared thermometer measures one selected point at a time.

It may miss a small hotspot inside a large switchboard or network rack.

Better Approach

Use a thermal camera such as the Noyafa NF-522 to scan the wider temperature pattern, then investigate the abnormal area further.

11. Ignoring Thermal Reflections

Shiny metal surfaces may reflect heat from:

  • The technician

  • Nearby equipment

  • Lighting

  • Other hot surfaces

Better Approach

Change the viewing angle and compare the result from another position before recording a confirmed hotspot.

12. Disconnecting Network Cables Without Verification

Disconnecting the wrong cable may interrupt:

  • Server connection

  • IP camera

  • Wireless access point

  • Access-control system

  • Building-management device

Better Approach

Verify using:

  • Rack records

  • Cable label

  • Cable tracer

  • Port identification

  • Wire-map test

  • Remote identifier

13. Trusting Old Cable Labels

Rack connections may change without documentation being updated.

Better Approach

Use a Noyafa NF-8209 Pro or Noyafa NF-8506 to confirm the cable before relabelling or disconnecting it.

14. Assuming a Passed Continuity Test Confirms Full Cable Performance

A simple tester may confirm that conductors connect from end to end, but it may not prove:

  • Required network speed

  • PoE performance under load

  • Cable category compliance

  • Absence of split pairs

  • Standards-compliant installation

Better Approach

Select the correct level of tester for troubleshooting or formal cable certification.

15. Replacing an a PoE Device Before Testing the Connection

An offline IP camera or access point may be caused by:

  • Damaged cable

  • Poor connector

  • Disabled PoE port

  • Insufficient switch power budget

  • Incorrect network setting

  • Faulty patch cord

Better Approach

Test the cable, switch port and PoE source separately before replacing the device.

16. Using Only a Network Cable Tester for CCTV Problems

A cable tester cannot normally display the camera image or confirm the complete camera configuration.

Better Approach

Use a CCTV tester such as the Noyafa NF-IPC728HSO when image checking and camera diagnosis are required.

17. Applying Insulation-Test Voltage to Connected Electronics

An insulation resistance tester can damage:

  • Servers

  • UPS electronics

  • Network switches

  • Variable-speed drives

  • Control boards

  • Monitoring systems

  • Surge-protection devices

Better Approach

Identify the circuit, isolate it and disconnect sensitive equipment according to the manufacturer’s procedure before testing.

18. Using a Non-Contact Voltage Detector as Proof of Isolation

A non-contact detector provides only an initial indication.

Better Approach

Follow the approved isolation and prove-dead procedure using a suitable voltage tester.

19. Buying an AC-Only Clamp Meter for Battery Work

UPS battery systems require DC-current measurement.

Better Approach

Confirm that the selected clamp meter supports:

  • DC current

  • Required current range

  • Suitable low-current resolution

  • Correct jaw size

  • Proper zeroing

20. Clamping Around Multiple Conductors

Clamping around outgoing and returning conductors together may cause their magnetic fields to cancel, producing a zero or incorrect reading.

Better Approach

Clamp around one conductor only, unless the approved test method specifically requires otherwise.

Record:

  • Circuit identification

  • AC or DC current

  • Measurement point

  • Equipment operating mode

  • Electrical load

  • Date and time

21. Comparing Electrical Measurements Under Different Loads

Current and temperature naturally change when equipment load changes.

A UPS inspected at 30% load should not be compared directly with a previous result recorded at 80% load without considering the difference.

Better Approach

Document the operating condition together with every electrical and thermal measurement.

22. Ignoring Phase Imbalance

Checking only the total load may hide a significant difference between individual phases.

Phase imbalance may contribute to:

  • Uneven cable heating

  • Higher neutral current

  • Transformer heating

  • Reduced electrical efficiency

  • Overloading of one phase

Better Approach

Use a suitable clamp meter or power quality analyzer to record each phase separately.

23. Using a Multimeter Instead of an Insulation Resistance Tester

A digital multimeter measures ordinary resistance at a low test voltage. It does not provide the same assessment as a dedicated insulation resistance tester.

Better Approach

Use an insulation resistance tester for approved isolated cable and motor circuits, following the correct test voltage and safety procedure.

24. Using an Insulation Tester to Test Ground Resistance

An insulation resistance tester and an earth resistance tester perform different functions.

Better Approach

Use:

  • Insulation resistance tester for cable, motor and selected equipment insulation

  • Earth resistance tester for earth electrodes and grounding systems

25. Assuming One Earth-Test Method Suits Every Installation

A clamp-on earth tester may not provide a valid result for a single isolated electrode without a parallel return path.

Better Approach

Review the grounding-system design before selecting:

  • Three-pole testing

  • Four-pole testing

  • Fall-of-potential testing

  • Selective testing

  • Clamp-on earth testing

26. Recording Only “Pass” or “Fail”

A pass/fail entry provides little information for future comparison.

Better Approach

Record the actual:

  • Temperature

  • Humidity

  • Current

  • Voltage

  • Resistance

  • Air velocity

  • Differential pressure

  • Sound level

  • Vibration value

  • Cable-test result

Trend data can reveal gradual deterioration before a result reaches the failure limit.

27. Failing to Identify the Measurement Location

A reading without an exact location cannot be repeated reliably.

Better Approach

Record details such as:

  • Room

  • Rack

  • Panel

  • Circuit

  • Phase

  • Terminal

  • Rack height

  • Front or rear

  • Distance from equipment

  • Airflow or pressure test points

28. Comparing Measurements in Different Units

Air velocity, pressure, temperature and electrical readings may be displayed in different units.

Better Approach

Use consistent units throughout the maintenance report and clearly state any conversion.

29. Ignoring Instrument Settings

Incorrect settings may produce misleading measurements.

Common examples include:

  • Wrong AC or DC selection

  • Incorrect current range

  • Wrong sound weighting

  • Incorrect airflow unit

  • Reversed differential-pressure ports

  • Incorrect thermal emissivity

  • Wrong data-logger interval

Better Approach

Record the important instrument settings with the result.

30. Failing to Zero the Instrument

Some instruments require zeroing before use, including:

  • DC clamp meters

  • Differential pressure meters

  • Selected vibration instruments

  • Certain sensors

Better Approach

Follow the manufacturer’s zeroing procedure before measurement and repeat it when operating conditions change.

31. Using Damaged Test Leads or Accessories

Damaged leads, pressure tubes, probes and connectors can create incorrect readings or safety risks.

Better Approach

Inspect before use:

  • Test-lead insulation

  • Probe tips

  • Clamp jaws

  • Pressure tubing

  • Temperature probes

  • Network connectors

  • Batteries

  • Chargers

Remove defective accessories from service.

32. Ignoring Instrument Range and Safety Rating

An instrument may provide the required function but still be unsuitable for the circuit voltage, current or electrical environment.

Better Approach

Confirm:

  • Measurement range

  • Maximum voltage

  • Current capacity

  • Measurement category

  • Probe rating

  • Accessory rating

  • Environmental limitations

33. Performing Tests Without Reviewing Manufacturer Instructions

Different UPS systems, batteries, transformers and cooling units may require different procedures.

Better Approach

Review:

  • Equipment manual

  • Test-instrument manual

  • Site maintenance procedure

  • Electrical drawings

  • Previous test records

  • Applicable safety requirements

34. Treating Thermal Imaging as a Complete Diagnosis

A thermal camera identifies abnormal heat but cannot always determine whether it is caused by:

  • High load

  • Loose connection

  • Poor ventilation

  • Internal component failure

  • Surface reflection

Better Approach

Confirm thermal findings using suitable current, voltage, airflow or physical inspection methods.

35. Ignoring Mechanical Vibration

Abnormal cooling-fan, pump or compressor vibration can develop before the equipment fails.

Better Approach

Use a vibration meter at consistent measurement points and compare results over time.

Sound, vibration, temperature and electrical current should be reviewed together when troubleshooting rotating equipment.

36. Judging Equipment Condition Only by Noise

A noisy fan may be defective, but noise may also increase because of higher speed, airflow restriction or operating load.

Better Approach

Combine a sound level meter with:

  • Vibration measurement

  • Thermal inspection

  • Airflow measurement

  • Electrical-current checking

  • Visual inspection

37. Comparing Noise Readings From Different Distances

Sound level changes with measurement position and surrounding surfaces.

Better Approach

During every inspection, record:

  • Distance from equipment

  • Meter height

  • Front, side or rear position

  • Equipment load

  • Door condition

  • Other operating equipment

38. Ignoring UPS Battery-Room Temperature

The general server room may be within normal condition while the battery area is too warm.

Better Approach

Use a separate temperature or temperature-and-humidity logger near the battery bank.

Inspect individual batteries and connections thermally.

39. Assuming Normal Battery Voltage Means Good Battery Condition

A battery may show a normal voltage while having reduced capacity or increased internal resistance.

Better Approach

Consider:

  • Battery voltage

  • Temperature

  • Internal resistance or conductance

  • Charging current

  • Physical condition

  • Installation age

  • Discharge-test history

40. Replacing One Battery Without Reviewing the Complete String

One failed battery may be part of a wider age or environmental problem.

Better Approach

Compare all batteries in the string and review the manufacturer’s replacement recommendations.

41. Relying Only on Generator No-Load Testing

A generator may start successfully but still experience problems when carrying the data-centre load.

Better Approach

Where included in the approved procedure, record under representative load:

  • Voltage

  • Frequency

  • Phase currents

  • Power factor

  • Temperature

  • Noise

  • Vibration

  • Cooling performance

42. Ignoring the Automatic Transfer Switch

A reliable generator is not useful if the transfer system fails.

Better Approach

Include the automatic transfer switch in the approved generator-maintenance and integrated-systems testing programme.

43. Failing to Review UPS and Generator Event Logs

Intermittent power problems may disappear before a technician arrives.

Better Approach

Compare instrument records with:

  • UPS events

  • Generator start time

  • Transfer-switch operation

  • Utility interruption

  • Cooling-system start-up

  • Equipment alarms

44. Using Spot Measurements for an Intermittent Electrical Problem

A multimeter or clamp meter shows only the current condition.

Better Approach

Use a power quality analyzer or suitable logging instrument when investigating:

  • Repeated UPS transfers

  • Voltage sags

  • Phase imbalance

  • Harmonics

  • High neutral current

  • Intermittent breaker trips

45. Collecting Data Without Analysing It

Measurements provide no benefit if they are stored without review.

Better Approach

After every inspection:

  1. Compare with previous results.

  2. Identify significant changes.

  3. Classify findings by priority.

  4. Assign corrective action.

  5. Set a completion date.

  6. Plan verification testing.

46. Writing “Normal” Without Actual Measurements

This makes future comparison impossible.

Better Approach

Write the actual value, measurement point and operating condition.

For example:

“Rack A03 front-top temperature measured 27.4°C at 2:30 PM while CRAC-1 and CRAC-2 were operating.”

47. Saving Thermal Images Without Equipment Identification

A thermal image may become useless if the equipment and location cannot be identified later.

Better Approach

Record:

  • Asset number

  • Panel or rack

  • Circuit or phase

  • Thermal image

  • Visual image

  • Load

  • Ambient temperature

  • Date and time

48. Failing to Update Rack and Cable Records

After moving equipment or changing switch ports, outdated documents can create future maintenance risks.

Better Approach

Update immediately:

  • Rack diagram

  • Patch-panel schedule

  • Switch-port list

  • Cable labels

  • PDU outlet record

  • Equipment inventory

49. Closing Findings Without Retesting

A reported repair does not prove that the original condition has been corrected.

Better Approach

Repeat the relevant:

  • Thermal scan

  • Temperature monitoring

  • Airflow measurement

  • Electrical test

  • Network cable test

  • CCTV check

  • Sound or vibration measurement

Record the final result before closing the finding.

50. Using the Same Maintenance Frequency for Every Asset

A critical UPS terminal with a previous hotspot requires more attention than a stable, lightly loaded circuit.

Better Approach

Set the inspection frequency according to:

  • Equipment criticality

  • Fault history

  • Age

  • Electrical load

  • Environmental condition

  • Manufacturer recommendation

  • Consequence of failure

Recommended Data Centre Maintenance Tool Combination

A complete toolkit may include:

  • Noyafa NF-522 Thermal Camera

  • Noyafa NF-8209 Pro Network Cable Tester

  • Noyafa NF-8506 Network Cable Tester

  • Noyafa NF-IPC728HSO CCTV Tester

  • Elitech RC-5 Temperature Data Logger

  • Elitech GSP-6 Pro Temperature and Humidity Data Logger

  • Temperature and humidity meter

  • Airflow meter

  • Differential pressure meter

  • Sound level meter

  • Vibration meter

  • AC/DC clamp meter

  • Digital multimeter

  • Insulation resistance tester

  • Earth resistance tester

  • Power quality analyzer

The correct selection depends on the technician’s authorised scope.

A Better Data Centre Maintenance Process

Use this sequence:

  1. Define the equipment and reported problem.

  2. Review drawings and previous records.

  3. Confirm safety and authorisation.

  4. Conduct a visual inspection.

  5. Measure the relevant condition.

  6. Record the exact test location.

  7. Compare with similar equipment and previous results.

  8. Confirm the possible cause using another method.

  9. Classify the finding.

  10. Assign corrective action.

  11. Retest after correction.

  12. Update the maintenance record.

Prevent Small Mistakes From Creating Larger Failures

Effective data-centre maintenance depends on more than owning good instruments.

The instruments must be selected correctly, positioned correctly and used under clearly recorded operating conditions.

By avoiding common mistakes in thermal inspection, network testing, environmental monitoring, airflow measurement and electrical testing, maintenance teams can produce more reliable evidence and reduce the risk of repeated faults or unexpected downtime.

Contact MTM Precision

MTM Precision Sdn. Bhd.

Showroom & Service Centre

No. 29-1 & 29-2, Jalan Bandar 18,
Pusat Bandar Puchong,
47160 Puchong, Selangor, Malaysia

🌐 Website: www.mtmpre.com.my
📧 Email: mtmpre@yahoo.com
📱 WhatsApp: +6016-660 7346

02 Sep 2026