Sokkia B40A How to Calculate RL, HI, Backsight & Foresight Malaysia

# Sokkia B40A How to Calculate RL, HI, Backsight & Foresight Malaysia

 

## Quick Answer

 

When using a **Sokkia B40A Automatic Level**, a common construction levelling method uses:

 

**RL = Reduced Level**

 

**BS = Backsight**

 

**HI = Height of Instrument**

 

**FS = Foresight**

 

A simplified calculation is:

 

## **HI = Known RL + Backsight**

 

Then:

 

## **New RL = HI − Staff Reading**

 

Example:

 

**Benchmark RL = 100.000 m**

 

**Backsight = 1.250 m**

 

Therefore:

 

## **HI = 100.000 + 1.250 = 101.250 m**

 

If the next staff reading is:

 

**1.850 m**

 

then:

 

## **New RL = 101.250 − 1.850 = 99.400 m**

 

This basic principle is widely used for construction elevation work.

 

---

 

# Sokkia B40A at a Glance

 

**Magnification:** **24x**

 

**Objective Aperture:** **32 mm**

 

**Levelling Accuracy:** **Approx. 2.0 mm / 1 km double-run**

 

**Minimum Focus:** **Approx. 0.2 m from telescope end**

 

**Compensator:** **Automatic pendulum system with magnetic damping**

 

**Compensator Working Range:** **±15′**

 

**Water Resistance:** **IPX6**

 

**Typical Applications:** **Construction • Foundation • Earthwork • Drainage • Roadwork • Factory Projects**

 

A practical levelling setup is:

 

## **Sokkia B40A + 5m Levelling Staff + Survey Tripod**

 

---

 

# What Is RL?

 

## **RL = REDUCED LEVEL**

 

Reduced Level represents the elevation of a point relative to the reference datum being used for the project.

 

For example:

 

**Benchmark RL = 100.000 m**

 

Another point may have:

 

**RL = 99.500 m**

 

This means the second point is **0.500 m lower** than the benchmark within that reference system.

 

RL allows different construction points to be compared using a common vertical reference.

 

---

 

# What Is a Benchmark?

 

A **benchmark** is a reference point with a known elevation.

 

Construction levelling often starts from this known reference.

 

For example:

 

## **BM RL = 100.000 m**

 

The B40A and levelling staff can then be used to transfer elevation information from this benchmark to other locations.

 

A benchmark may ultimately be used to establish or verify:

 

**Foundation Level**

 

**Concrete Level**

 

**Earthwork Level**

 

**Drainage Level**

 

**Road Formation**

 

**Building Reference Levels**

 

---

 

# What Is a Temporary Benchmark?

 

Large construction sites may require additional reference points.

 

A **Temporary Benchmark**, commonly called a **TBM**, can provide a convenient working elevation reference closer to the active construction area.

 

A typical sequence may be:

 

## **PROJECT BENCHMARK → TBM → WORK AREA**

 

Temporary benchmarks should be:

 

**Stable**

 

**Clearly Identified**

 

**Protected**

 

**Checked According to Project Procedure**

 

If the TBM moves, measurements based on it may also become unreliable.

 

---

 

# What Is Backsight?

 

## **BS = BACKSIGHT**

 

A backsight is a staff reading taken on a point of known or established elevation, commonly used to establish the Height of Instrument.

 

Example:

 

**Known Benchmark RL = 50.000 m**

 

**Backsight = 1.325 m**

 

Then:

 

## **HI = 50.000 + 1.325**

 

## **HI = 51.325 m**

 

The backsight connects your instrument setup to the known elevation reference.

 

---

 

# What Is Height of Instrument?

 

## **HI = HEIGHT OF INSTRUMENT**

 

In the HI method, this represents the calculated elevation of the instrument's horizontal line of sight.

 

The basic formula is:

 

# **HI = RL + BS**

 

Example:

 

**RL = 100.000 m**

 

**BS = 1.500 m**

 

Therefore:

 

## **HI = 101.500 m**

 

Once HI is established, elevations of other observed points can be calculated from their staff readings.

 

---

 

# What Is Foresight?

 

## **FS = FORESIGHT**

 

A foresight is typically a staff reading taken on a point whose elevation is to be established, often including a change point before moving the instrument.

 

If:

 

**HI = 101.500 m**

 

and:

 

**FS = 2.000 m**

 

then:

 

## **RL = HI − FS**

 

Therefore:

 

## **RL = 101.500 − 2.000**

 

## **RL = 99.500 m**

 

---

 

# What Is Intermediate Sight?

 

You may also encounter:

 

## **IS = INTERMEDIATE SIGHT**

 

An intermediate sight is a reading taken from the same instrument setup on an additional point whose elevation is required.

 

The basic calculation remains:

 

## **RL = HI − STAFF READING**

 

Example:

 

**HI = 101.500 m**

 

**IS = 1.750 m**

 

Therefore:

 

## **RL = 99.750 m**

 

This can be useful when checking multiple construction points from one instrument setup.

 

---

 

# Easy Formula to Remember

 

For the HI method, remember these two formulas:

 

# **HI = RL + BS**

 

and:

 

# **RL = HI − FS / IS**

 

That gives the basic flow:

 

## **KNOWN RL + BS → HI**

 

then:

 

## **HI − STAFF READING → NEW RL**

 

---

 

# Simple Sokkia B40A Levelling Example

 

Suppose:

 

**Benchmark RL = 20.000 m**

 

The B40A is set up and the staff reading on the benchmark is:

 

**BS = 1.425 m**

 

Calculate HI:

 

## **20.000 + 1.425 = 21.425 m**

 

Now move the staff to Point A.

 

Reading:

 

**IS = 1.875 m**

 

Therefore:

 

## **Point A RL = 21.425 − 1.875**

 

## **Point A RL = 19.550 m**

 

Move the staff to Point B.

 

Reading:

 

**IS = 2.125 m**

 

Therefore:

 

## **Point B RL = 21.425 − 2.125**

 

## **Point B RL = 19.300 m**

 

The same instrument setup can therefore establish elevations at multiple points.

 

---

 

# Example Levelling Field Book

 

A simplified field record may look like this:

 

| Point | BS | IS | FS | HI | RL |

|---|---:|---:|---:|---:|---:|

| BM | 1.425 | – | – | 21.425 | 20.000 |

| A | – | 1.875 | – | 21.425 | 19.550 |

| B | – | 2.125 | – | 21.425 | 19.300 |

| CP1 | – | – | 1.625 | 21.425 | 19.800 |

 

This is a simplified educational example.

 

Actual site recording procedures should follow the company's or project's required surveying method.

 

---

 

# What Is a Change Point?

 

When the next required location cannot be observed conveniently from the existing instrument position, the automatic level may need to be moved.

 

A stable point can be used as a:

 

## **CHANGE POINT / TURNING POINT**

 

The general sequence becomes:

 

**Old Instrument Setup**

 

↓

 

**Foresight to Change Point**

 

↓

 

**Calculate Change Point RL**

 

↓

 

**Move B40A**

 

↓

 

**Backsight to Same Change Point**

 

↓

 

**Calculate New HI**

 

↓

 

**Continue Levelling**

 

This allows the elevation reference to be transferred across a larger site.

 

---

 

# Change Point Example

 

Assume:

 

**Current HI = 51.500 m**

 

Foresight to CP1:

 

**FS = 2.000 m**

 

Therefore:

 

## **CP1 RL = 51.500 − 2.000**

 

## **CP1 RL = 49.500 m**

 

Now move the B40A.

 

Take a new backsight on CP1:

 

**BS = 1.250 m**

 

New HI:

 

## **49.500 + 1.250 = 50.750 m**

 

You can now continue measuring from the new instrument setup.

 

---

 

# Why Is This Useful for Construction?

 

Once you understand:

 

## **RL + BS = HI**

 

and:

 

## **HI − READING = RL**

 

the same principle can support many construction applications.

 

For example:

 

### **Foundation**

 

Check excavation and structural elevations.

 

### **Concrete**

 

Compare slab or structural points with required levels.

 

### **Earthwork**

 

Determine existing ground elevations and compare against formation levels.

 

### **Drainage**

 

Transfer elevations between benchmarks, manholes and drainage points.

 

### **Roadwork**

 

Check formation and construction elevations.

 

### **Factory Construction**

 

Transfer elevation references across industrial construction areas.

 

---

 

# RL Example for Cut & Fill

 

Suppose:

 

**Measured Existing Ground RL = 25.650 m**

 

Required formation:

 

**Design RL = 25.200 m**

 

Difference:

 

## **25.650 − 25.200 = 0.450 m**

 

The ground is higher than the required level.

 

Conceptually:

 

## **CUT = 0.450 m**

 

Now assume:

 

**Existing Ground RL = 24.900 m**

 

**Design RL = 25.200 m**

 

Difference:

 

## **25.200 − 24.900 = 0.300 m**

 

Conceptually:

 

## **FILL = 0.300 m**

 

The actual construction work must follow the project specifications.

 

---

 

# RL Example for Drainage

 

Suppose the approved drawing gives a required drainage point elevation.

 

The contractor can use:

 

**Known Benchmark**

 

↓

 

**Backsight**

 

↓

 

**Calculate HI**

 

↓

 

**Take Staff Reading at Drainage Point**

 

↓

 

**Calculate Actual RL**

 

↓

 

**Compare Actual RL with Design RL**

 

The B40A provides the elevation measurement.

 

## **IT DOES NOT DETERMINE THE REQUIRED DRAINAGE GRADIENT.**

 

The design must come from the approved engineering documents.

 

---

 

# Common Calculation Mistake: Adding Instead of Subtracting

 

A very common beginner mistake is confusing the formulas.

 

Remember:

 

## **KNOWN RL + BACKSIGHT = HI**

 

Then:

 

## **HI − STAFF READING = POINT RL**

 

A larger staff reading generally means the observed ground point is lower relative to the same line of sight.

 

This simple concept makes the calculations easier to understand.

 

---

 

# Common Mistake: Wrong Benchmark RL

 

Even perfect arithmetic will produce the wrong result if you start from the wrong benchmark.

 

Before beginning:

 

**Confirm Benchmark ID**

 

**Confirm Benchmark RL**

 

**Confirm Project Datum**

 

**Confirm Reference Has Not Been Disturbed**

 

## **CORRECT CALCULATION + WRONG BENCHMARK = WRONG RESULT**

 

---

 

# Common Mistake: Staff Not Vertical

 

If the levelling staff is tilted, the observed reading can be affected.

 

Keep the staff vertical during important observations.

 

On uneven construction ground, this deserves extra attention.

 

The B40A can be correctly adjusted and still produce poor field results if the staff is used incorrectly.

 

---

 

# Common Mistake: Unstable Tripod

 

Check:

 

**Tripod Legs**

 

**Ground Stability**

 

**Tripod Head**

 

**Instrument Mounting**

 

Avoid unstable areas affected by:

 

**Heavy Machinery**

 

**Soft Ground**

 

**Vehicle Movement**

 

**Construction Vibration**

 

A stable setup is essential for consistent readings.

 

---

 

# Common Mistake: Very Long Sight Distances

 

Large sites can tempt operators to observe over excessive distances.

 

But longer is not automatically better.

 

Under Malaysian conditions, long observations can be affected by:

 

**Heat Shimmer**

 

**Atmospheric Distortion**

 

**Staff Visibility**

 

**Operator Reading Difficulty**

 

Where practical:

 

## **MOVE THE INSTRUMENT CLOSER.**

 

---

 

# Backsight & Foresight Distance

 

For good levelling practice, keep backsight and foresight distances **reasonably balanced where practical**.

 

Why?

 

Because certain systematic line-of-sight effects can be reduced when sight distances are similar.

 

This becomes particularly important when transferring elevations across multiple setups.

 

---

 

# How Do I Check My Calculation?

 

Field procedures may include arithmetic and closure checks.

 

At a basic level, review:

 

**Benchmark RL**

 

**Recorded BS**

 

**Recorded FS**

 

**HI Calculation**

 

**Point RL**

 

**Change Points**

 

Also confirm that values were entered into the correct field-book columns.

 

For project survey work, use the checking procedure required by the project or organisation.

 

---

 

# What If the Maths Is Correct but the RL Is Still Wrong?

 

Then investigate the measurement system.

 

Check:

 

**Benchmark**

 

**Staff**

 

**Tripod**

 

**Instrument Setup**

 

**Parallax**

 

**Heat Shimmer**

 

**Operator Reading**

 

**Collimation**

 

**Instrument Condition**

 

If the B40A has been dropped or repeatedly produces questionable results, perform an appropriate field check such as a **two-peg test** or arrange professional inspection.

 

---

 

# Is Sokkia B40A Suitable for Learning Levelling?

 

## **Yes.**

 

The B40A uses the same fundamental conventional levelling principles that apply to professional automatic-level work.

 

It can be used to understand:

 

**Benchmark**

 

**RL**

 

**BS**

 

**IS**

 

**FS**

 

**HI**

 

**Change Point**

 

**Elevation Transfer**

 

These concepts remain highly relevant to practical construction levelling.

 

---

 

# For Johor Contractors

 

Contractors in:

 

**Johor Bahru**

 

**Iskandar Puteri**

 

**Pasir Gudang**

 

**Kulai**

 

**Senai**

 

**Pengerang**

 

can use conventional RL and HI calculations for applications including:

 

**Building Construction**

 

**Factory Projects**

 

**Earthwork**

 

**Drainage**

 

**Roadwork**

 

**Infrastructure**

 

For teams training new site personnel, understanding **BS → HI → RL** is one of the most useful basic levelling concepts.

 

---

 

# For Penang Contractors

 

In:

 

**Bayan Lepas**

 

**Batu Kawan**

 

**Perai**

 

**Butterworth**

 

**Bukit Mertajam**

 

automatic-level calculations are relevant to:

 

**Factory Construction**

 

**Industrial Expansion**

 

**Warehouse Projects**

 

**Foundation**

 

**Concrete**

 

**Drainage**

 

**External Civil Works**

 

The same RL, HI, backsight and foresight principles apply regardless of the project type.

 

---

 

# FAQ – RL, HI, BS & FS

 

### **What does RL mean in surveying?**

 

**RL means Reduced Level.** It represents the elevation of a point relative to the reference datum used for the project.

 

### **What does BS mean?**

 

**BS means Backsight.** It is commonly a staff reading taken on a known or established elevation to determine HI.

 

### **What does FS mean?**

 

**FS means Foresight.** It is commonly the final reading from an instrument setup, often taken on a point whose RL is required or on a change point.

 

### **What does IS mean?**

 

**IS means Intermediate Sight**, a reading to another point taken between the backsight and foresight from the same setup.

 

### **How do you calculate HI?**

 

Use:

 

## **HI = Known RL + BS**

 

### **How do you calculate RL?**

 

Using the HI method:

 

## **RL = HI − Staff Reading**

 

### **Can B40A calculate RL automatically?**

 

**No.** The B40A is an optical automatic level. The operator observes the staff and performs or records the required calculations separately.

 

### **Can I use B40A for cut & fill?**

 

**Yes.** It can provide elevation measurements used to determine cut and fill depths.

 

---

 

# Who Is This Setup For?

 

## Recommended For

 

**Site Supervisors**

 

**Construction Contractors**

 

**Civil Contractors**

 

**Earthwork Contractors**

 

**Drainage Contractors**

 

**Road Contractors**

 

**Factory Contractors**

 

**Surveying Students & Trainees**

 

who need a professional conventional levelling setup.

 

---

 

# Complete Auto Level Setup

 

For conventional levelling, a practical package is:

 

## **Sokkia B40A**

 

+

 

## **5m Levelling Staff**

 

+

 

## **Survey Tripod**

 

Together, these provide the basic equipment required for staff-based elevation measurements.

 

---

 

# Buy, Equip or Service

 

### **Need Sokkia B40A?**

 

Ask MTM Precision for the current quotation.

 

### **Starting from Zero?**

 

Ask for:

 

## **B40A + 5m Staff + Survey Tripod**

 

### **Already Own an Automatic Level?**

 

If readings do not agree even after checking your calculations and field procedure, enquire about:

 

**Checking • Calibration • Technical Inspection • Repair**

 

Selected surveying brands supported include:

 

**Sokkia • Topcon • Nikon • Leica • Trimble • Pentax**

 

---

 

# Sokkia B40A Malaysia

 

MTM Precision supports customers throughout:

 

**Selangor • Kuala Lumpur • Johor • Penang • Perak • Negeri Sembilan • Melaka • Pahang • Kedah • Perlis • Terengganu • Sarawak • Sabah**

 

Focused coverage includes:

 

**Johor:** Johor Bahru, Iskandar Puteri, Pasir Gudang, Kulai, Senai and Pengerang.

 

**Penang:** Bayan Lepas, Batu Kawan, Perai, Butterworth and Bukit Mertajam.

 

---

 

# Contact MTM Precision

 

**MTM Precision Sdn Bhd**

 

Website: **www.mtmpre.com.my** 

Email: **mtmpre@yahoo.com** 

WhatsApp: **016-660 7346**

 

## Showroom & Service Centre

 

**No. 29-1 & 29-2, Jalan Bandar 18, 

Pusat Bandar Puchong, 

47160 Puchong, Selangor, Malaysia**

 

Contact MTM Precision for **Sokkia B40A, RL and construction levelling equipment, 5m levelling staffs, survey tripods, automatic level checking, calibration and surveying equipment in Johor, Penang and throughout Malaysia**.

12 Sep 2026