Liquid Cooling Commissioning Checklist for Tropical Data Centres Malaysia

Liquid Cooling Commissioning Checklist for Tropical Data Centres Malaysia


A data centre liquid cooling system should not be placed into full operation simply because the pumps are running and no visible leak has been found.


Before handover, the commissioning team should verify:


Is the coolant suitable for the system?


Is every rack receiving the required flow?


Can the system respond to changing IT loads?


Will the alarm and isolation functions operate during an actual fault?


For tropical data centres in Malaysia, commissioning must also consider high ambient temperature, humidity, water quality and the interaction between liquid cooling and existing air-cooling equipment.


This checklist provides a practical starting point for contractors, facility teams and commissioning personnel. The final procedure must always follow the system design, equipment manufacturer requirements and applicable project standards.


1. Review the System Design


Before carrying out physical tests, confirm the intended cooling arrangement.


The design documents should identify:


Cooling technology


Coolant type


Operating pressure


Required flow rate


Supply and return temperature limits


Coolant Distribution Unit capacity


Rack and manifold arrangement


Heat rejection system


Alarm and control sequence


Redundancy requirements


Common arrangements may include:


Direct-to-chip liquid cooling


Rear-door heat exchangers


Immersion cooling


In-row liquid cooling


Hybrid air and liquid cooling


Facility-water and technology-cooling loops


Technicians must understand which side of the system they are measuring.


The facility water system and technology cooling system may have different fluid quality, pressure and temperature requirements.


2. Verify Instrument Calibration Status


Commissioning decisions depend on reliable measurements.


Before testing begins, check the calibration or verification status of:


Temperature meters


Temperature data loggers


Flow meters


Pressure gauges


Differential pressure meters


pH meters


Electrical conductivity meters


Refractometers


Electrical power analysers


Vibration meters


Also confirm:


Instrument measuring range


Required accuracy


Sensor condition


Battery level


Data-logging settings


Correct time and date


Suitable probes and adapters


An instrument with an inappropriate range may display a value without providing the accuracy required for commissioning.


3. Inspect the Pipework and Connections


Carry out a visual inspection before pressurising or operating the system.


Check:


Pipe supports


Flexible hoses


Quick-disconnect couplings


Valves


Flanges


Manifolds


Drain points


Air vents


Insulation


Flow direction markings


Equipment labels


Look for:


Loose fittings


Damaged seals


Twisted hoses


Incorrect valve positions


Unsupported pipework


Sharp bends


Contact with electrical cables


Incomplete insulation


Signs of physical damage


The system layout should allow maintenance teams to access valves, filters, pumps and measuring points without disturbing nearby IT equipment.


4. Confirm System Cleanliness and Flushing


Construction debris, sealant, metal particles and other contamination may remain inside newly installed pipework.


Before connecting critical cold plates and rack equipment, confirm that the system has been flushed according to the project requirements.


The flushing process may involve checking:


Flow velocity


Filter condition


Differential pressure


Fluid clarity


Conductivity


pH


Particle contamination


Drain samples


Do not assume that clear-looking fluid is free from harmful contamination.


Fine particles may restrict cold plates or damage pumps even when the coolant appears clean.


5. Check Coolant Type and Concentration


Confirm that the coolant matches the approved specification.


Check:


Coolant product name


Batch information


Mixing ratio


Water source


Additive package


Material compatibility


Manufacturer approval


Where glycol concentration must be measured, use a refractometer suitable for the actual fluid.


Do not use an ethylene glycol scale for a propylene glycol mixture unless the instrument and method specifically support it.


Proprietary coolants may require a dedicated measurement method rather than a general-purpose refractometer.


6. Measure Coolant pH and Conductivity


Coolant chemistry can affect corrosion, scaling, deposits and electrical risk.


During commissioning, record:


Initial pH


Electrical conductivity


Coolant temperature


Measurement location


Time and date


Instrument used


Calibration status


Compare the results with the coolant or system manufacturer’s limits.


Do not apply general drinking-water or wastewater limits to a data centre cooling loop.


If the measured value is outside the specification, investigate:


Incorrect mixing


Contaminated filling equipment


Residual flushing chemicals


Unsuitable water


Corrosion products


Contact with incompatible materials


7. Pressure-Test the System


The pressure test helps confirm the integrity of pipes, hoses, valves and connections.


Before testing:


Confirm the approved test pressure


Isolate equipment that should not receive the test pressure


Use a suitable calibrated pressure instrument


Identify the test duration


Confirm the acceptable pressure loss


Establish a safe exclusion area


During the test, inspect common leak points such as:


Quick-disconnect couplings


Hose ends


Valves


Flanges


Manifold connections


Drain points


Sensor ports


Heat exchanger connections


A pressure drop does not always confirm an external leak.


Temperature changes, trapped air or measurement uncertainty may also affect the result.


8. Remove Trapped Air


Air trapped inside a liquid cooling system may cause:


Reduced heat-transfer performance


Unstable flow


Pump noise


Cavitation


Incorrect flow readings


Corrosion risk


Fluctuating pressure


Operate the approved vents and bleeding points according to the manufacturer’s procedure.


Observe whether:


Flow becomes stable


Pump noise decreases


Pressure fluctuation reduces


Temperature performance improves


Air continues to collect at high points


Repeated air accumulation may indicate a leak, poor system design or inadequate filling procedure.


9. Verify Pump Operation


Check every operating and standby pump.


Record:


Supply pressure


Return pressure


Differential pressure


Flow rate


Motor current


Power consumption


Pump speed


Vibration


Abnormal noise


Bearing or casing temperature


Possible warning signs include:


Unstable pressure


Excessive vibration


Grinding noise


Repeated starting and stopping


High motor current


Low flow despite high pump speed


Bubbles or cavitation sound


Do not treat a pump as acceptable based only on the fact that it rotates.


10. Balance Coolant Flow


Each rack or branch should receive the flow required by the system design.


Measure and compare:


Main-loop flow


Branch flow


Rack flow


Manifold flow


Flow before and after valve adjustment


Poor flow balance may cause some racks to overheat while others receive more coolant than necessary.


When adjusting valves, record:


Valve position


Flow before adjustment


Flow after adjustment


Pressure change


Temperature response


Random valve adjustment without measurement can make the system more difficult to troubleshoot later.


11. Measure Supply and Return Temperatures


Measure coolant temperature at consistent locations.


Important points may include:


CDU supply


CDU return


Rack manifold supply


Rack manifold return


Heat exchanger inlet


Heat exchanger outlet


Facility-water supply and return


Calculate the temperature difference:


ΔT = Return Temperature – Supply Temperature


A small or large ΔT is not automatically good or bad.


Interpret the result together with:


IT heat load


Coolant flow


Pump operation


Control settings


Manufacturer requirements


A low ΔT may indicate excessive flow or low IT load.


A high ΔT may indicate insufficient flow, high heat load or a restriction.


12. Test Under Different IT Loads


A liquid cooling system may appear stable at low load but fail when the rack power increases.


Where the project procedure permits, test the system under several operating conditions:


Low IT load


Normal IT load


High IT load


Rapid load increase


Load reduction


Partial system operation


Record:


IT power


Coolant flow


Supply temperature


Return temperature


Pressure


Pump speed


CDU power


Alarm status


Stabilisation time


The test should confirm that the cooling system responds before component temperatures reach unsafe levels.


13. Check Dynamic Response


Modern AI workloads can change quickly.


The commissioning team should determine:


How long does the cooling system take to respond after the IT load increases?


Monitor the sequence:


Load Change → Temperature Rise → Control Response → Flow Adjustment → Temperature Stabilisation


A delayed response may be caused by:


Slow temperature sensors


Poor sensor placement


Control-system delay


Incorrect PID settings


Insufficient pump capacity


Slow valve movement


Communication problems


A normal final temperature does not necessarily mean the response time is acceptable.


14. Test Leak Detection


Every leak detector should be functionally tested according to the approved method.


Check:


Point sensors


Leak detection cables


Drip-tray sensors


CDU internal sensors


Rack-level sensors


Floor-level sensors


Confirm the complete alarm path:


Sensor → Local Controller → BMS/DCIM → Alarm Notification → Response Team


Record:


Sensor identification


Test location


Alarm response time


Displayed alarm message


Notification received


Reset procedure


Final result


A sensor that detects liquid but sends the alarm to the wrong location has not passed a complete functional test.


15. Test Automatic Isolation Functions


Some systems may include automatic valves or pump shutdown functions.


Where applicable, simulate the approved fault conditions and confirm:


Isolation valve operation


Pump shutdown


Standby pump activation


Alarm transmission


System pressure response


Protection of unaffected racks


Recovery procedure


Automatic isolation should prevent the incident from spreading without creating another cooling failure.


16. Verify Redundancy and Failover


If the system is designed with redundant pumps, CDUs or power supplies, test the failover sequence.


Possible tests include:


Duty pump failure


Standby pump activation


CDU power interruption


Communication failure


Sensor failure


Control-system restart


Loss of one cooling branch


Record whether:


Cooling continues


Alarms activate correctly


Flow remains sufficient


Temperature remains controlled


Manual intervention is required


A standby unit that has never been tested should not be assumed to operate during an actual failure.


17. Inspect the System with a Thermal Camera


Carry out a thermal survey under representative load.


Check:


Rack connections


Manifolds


Pumps


Motors


Heat exchangers


Electrical panels


Insulated pipes


Valves and fittings


Look for:


Uneven thermal patterns


Hot connections


Poor insulation


Abnormal motor temperature


Branches with different cooling performance


Unexpected heat near couplings


Thermal imaging should supplement temperature, flow and pressure measurements rather than replace them.


18. Check Pump and Fan Vibration


Measure vibration on the CDU pumps and associated cooling equipment.


Use consistent:


Measurement points


Measurement directions


Instrument settings


Operating speeds


System loads


Record baseline readings during commissioning.


These baseline values can later help maintenance teams identify changes caused by:


Imbalance


Misalignment


Bearing wear


Looseness


Cavitation


Foundation problems


19. Measure Electrical Consumption


Record the power used by:


CDU


Pumps


Chillers


Dry coolers


Cooling-tower fans


Control equipment


Heat-rejection systems


Compare electrical consumption at different IT loads.


A liquid cooling system should be assessed based on overall performance, not only coolant temperature.


Higher pump speeds may improve cooling while increasing energy use. The selected operating point should satisfy both thermal and efficiency requirements.


20. Confirm Data Logging and Time Synchronisation


Temperature, flow, pressure, electrical and control-system data should use aligned timestamps.


This allows engineers to determine:


Which event happened first


How quickly the system reacted


How long the temperature remained high


Whether the alarm was delayed


Whether pump or valve movement corrected the condition


Incorrect timestamps can make a genuine system problem appear unrelated.


Liquid Cooling Commissioning Records


The final commissioning report should include:


System description


Equipment identification


Approved operating limits


Instrument list


Calibration information


Test methods


Measurement results


Alarm test results


Failover test results


Photos and thermal images


Outstanding defects


Corrective actions


Retest results


Final acceptance status


Do not rely only on handwritten readings without identifying the instrument, time, operating condition and measurement location.


Common Liquid Cooling Commissioning Problems


Frequent problems may include:


Incorrect coolant concentration


High conductivity


Unstable pH


Trapped air


Low branch flow


Blocked filters


Reversed flow direction


Incorrect valve positions


Pump cavitation


Delayed temperature response


Leak alarms sent to the wrong destination


Standby equipment not activating


Incomplete calibration records


Finding these issues during commissioning is safer and less expensive than discovering them after critical IT equipment is operating at full load.


Need Instruments for Liquid Cooling Commissioning?


Send MTM Precision:


Required measurement


Expected range


Coolant type


Pipe or connection information


Commissioning application


Quantity


If available, send the system diagram, specification or site photo through WhatsApp.


This allows us to understand whether you require temperature, flow, pressure, coolant quality, thermal imaging, vibration, leak detection or electrical measurement instruments.


MTM Precision supplies industrial testing instruments for data centre commissioning and maintenance in Malaysia, supporting customers in Selangor, Kuala Lumpur, Johor, Penang, Melaka, Negeri Sembilan, Perak, Pahang, Kelantan, Terengganu, Kedah, Perlis, Sabah and Sarawak.


MTM Precision – Data Centre Liquid Cooling Testing Malaysia


Showroom & Service Centre:

No. 29-1 & 29-2, Jalan Bandar 18,

Pusat Bandar Puchong,

47160 Puchong, Selangor, Malaysia.


Tel: 03-8080 7172

WhatsApp: +6016-660 7346

Email: mtmpre@yahoo.com

Website: www.mtmpre.com.my


Send us your measurement requirement + range + coolant type + application photo for liquid cooling commissioning instrument selection in Malaysia.



02 Oct 2026