Liquid Cooling Commissioning Checklist for Tropical Data Centres Malaysia
Liquid Cooling Commissioning Checklist for Tropical Data Centres Malaysia
A data centre liquid cooling system should not be placed into full operation simply because the pumps are running and no visible leak has been found.
Before handover, the commissioning team should verify:
Is the coolant suitable for the system?
Is every rack receiving the required flow?
Can the system respond to changing IT loads?
Will the alarm and isolation functions operate during an actual fault?
For tropical data centres in Malaysia, commissioning must also consider high ambient temperature, humidity, water quality and the interaction between liquid cooling and existing air-cooling equipment.
This checklist provides a practical starting point for contractors, facility teams and commissioning personnel. The final procedure must always follow the system design, equipment manufacturer requirements and applicable project standards.
1. Review the System Design
Before carrying out physical tests, confirm the intended cooling arrangement.
The design documents should identify:
Cooling technology
Coolant type
Operating pressure
Required flow rate
Supply and return temperature limits
Coolant Distribution Unit capacity
Rack and manifold arrangement
Heat rejection system
Alarm and control sequence
Redundancy requirements
Common arrangements may include:
Direct-to-chip liquid cooling
Rear-door heat exchangers
Immersion cooling
In-row liquid cooling
Hybrid air and liquid cooling
Facility-water and technology-cooling loops
Technicians must understand which side of the system they are measuring.
The facility water system and technology cooling system may have different fluid quality, pressure and temperature requirements.
2. Verify Instrument Calibration Status
Commissioning decisions depend on reliable measurements.
Before testing begins, check the calibration or verification status of:
Temperature meters
Temperature data loggers
Flow meters
Pressure gauges
Differential pressure meters
pH meters
Electrical conductivity meters
Refractometers
Electrical power analysers
Vibration meters
Also confirm:
Instrument measuring range
Required accuracy
Sensor condition
Battery level
Data-logging settings
Correct time and date
Suitable probes and adapters
An instrument with an inappropriate range may display a value without providing the accuracy required for commissioning.
3. Inspect the Pipework and Connections
Carry out a visual inspection before pressurising or operating the system.
Check:
Pipe supports
Flexible hoses
Quick-disconnect couplings
Valves
Flanges
Manifolds
Drain points
Air vents
Insulation
Flow direction markings
Equipment labels
Look for:
Loose fittings
Damaged seals
Twisted hoses
Incorrect valve positions
Unsupported pipework
Sharp bends
Contact with electrical cables
Incomplete insulation
Signs of physical damage
The system layout should allow maintenance teams to access valves, filters, pumps and measuring points without disturbing nearby IT equipment.
4. Confirm System Cleanliness and Flushing
Construction debris, sealant, metal particles and other contamination may remain inside newly installed pipework.
Before connecting critical cold plates and rack equipment, confirm that the system has been flushed according to the project requirements.
The flushing process may involve checking:
Flow velocity
Filter condition
Differential pressure
Fluid clarity
Conductivity
pH
Particle contamination
Drain samples
Do not assume that clear-looking fluid is free from harmful contamination.
Fine particles may restrict cold plates or damage pumps even when the coolant appears clean.
5. Check Coolant Type and Concentration
Confirm that the coolant matches the approved specification.
Check:
Coolant product name
Batch information
Mixing ratio
Water source
Additive package
Material compatibility
Manufacturer approval
Where glycol concentration must be measured, use a refractometer suitable for the actual fluid.
Do not use an ethylene glycol scale for a propylene glycol mixture unless the instrument and method specifically support it.
Proprietary coolants may require a dedicated measurement method rather than a general-purpose refractometer.
6. Measure Coolant pH and Conductivity
Coolant chemistry can affect corrosion, scaling, deposits and electrical risk.
During commissioning, record:
Initial pH
Electrical conductivity
Coolant temperature
Measurement location
Time and date
Instrument used
Calibration status
Compare the results with the coolant or system manufacturer’s limits.
Do not apply general drinking-water or wastewater limits to a data centre cooling loop.
If the measured value is outside the specification, investigate:
Incorrect mixing
Contaminated filling equipment
Residual flushing chemicals
Unsuitable water
Corrosion products
Contact with incompatible materials
7. Pressure-Test the System
The pressure test helps confirm the integrity of pipes, hoses, valves and connections.
Before testing:
Confirm the approved test pressure
Isolate equipment that should not receive the test pressure
Use a suitable calibrated pressure instrument
Identify the test duration
Confirm the acceptable pressure loss
Establish a safe exclusion area
During the test, inspect common leak points such as:
Quick-disconnect couplings
Hose ends
Valves
Flanges
Manifold connections
Drain points
Sensor ports
Heat exchanger connections
A pressure drop does not always confirm an external leak.
Temperature changes, trapped air or measurement uncertainty may also affect the result.
8. Remove Trapped Air
Air trapped inside a liquid cooling system may cause:
Reduced heat-transfer performance
Unstable flow
Pump noise
Cavitation
Incorrect flow readings
Corrosion risk
Fluctuating pressure
Operate the approved vents and bleeding points according to the manufacturer’s procedure.
Observe whether:
Flow becomes stable
Pump noise decreases
Pressure fluctuation reduces
Temperature performance improves
Air continues to collect at high points
Repeated air accumulation may indicate a leak, poor system design or inadequate filling procedure.
9. Verify Pump Operation
Check every operating and standby pump.
Record:
Supply pressure
Return pressure
Differential pressure
Flow rate
Motor current
Power consumption
Pump speed
Vibration
Abnormal noise
Bearing or casing temperature
Possible warning signs include:
Unstable pressure
Excessive vibration
Grinding noise
Repeated starting and stopping
High motor current
Low flow despite high pump speed
Bubbles or cavitation sound
Do not treat a pump as acceptable based only on the fact that it rotates.
10. Balance Coolant Flow
Each rack or branch should receive the flow required by the system design.
Measure and compare:
Main-loop flow
Branch flow
Rack flow
Manifold flow
Flow before and after valve adjustment
Poor flow balance may cause some racks to overheat while others receive more coolant than necessary.
When adjusting valves, record:
Valve position
Flow before adjustment
Flow after adjustment
Pressure change
Temperature response
Random valve adjustment without measurement can make the system more difficult to troubleshoot later.
11. Measure Supply and Return Temperatures
Measure coolant temperature at consistent locations.
Important points may include:
CDU supply
CDU return
Rack manifold supply
Rack manifold return
Heat exchanger inlet
Heat exchanger outlet
Facility-water supply and return
Calculate the temperature difference:
ΔT = Return Temperature – Supply Temperature
A small or large ΔT is not automatically good or bad.
Interpret the result together with:
IT heat load
Coolant flow
Pump operation
Control settings
Manufacturer requirements
A low ΔT may indicate excessive flow or low IT load.
A high ΔT may indicate insufficient flow, high heat load or a restriction.
12. Test Under Different IT Loads
A liquid cooling system may appear stable at low load but fail when the rack power increases.
Where the project procedure permits, test the system under several operating conditions:
Low IT load
Normal IT load
High IT load
Rapid load increase
Load reduction
Partial system operation
Record:
IT power
Coolant flow
Supply temperature
Return temperature
Pressure
Pump speed
CDU power
Alarm status
Stabilisation time
The test should confirm that the cooling system responds before component temperatures reach unsafe levels.
13. Check Dynamic Response
Modern AI workloads can change quickly.
The commissioning team should determine:
How long does the cooling system take to respond after the IT load increases?
Monitor the sequence:
Load Change → Temperature Rise → Control Response → Flow Adjustment → Temperature Stabilisation
A delayed response may be caused by:
Slow temperature sensors
Poor sensor placement
Control-system delay
Incorrect PID settings
Insufficient pump capacity
Slow valve movement
Communication problems
A normal final temperature does not necessarily mean the response time is acceptable.
14. Test Leak Detection
Every leak detector should be functionally tested according to the approved method.
Check:
Point sensors
Leak detection cables
Drip-tray sensors
CDU internal sensors
Rack-level sensors
Floor-level sensors
Confirm the complete alarm path:
Sensor → Local Controller → BMS/DCIM → Alarm Notification → Response Team
Record:
Sensor identification
Test location
Alarm response time
Displayed alarm message
Notification received
Reset procedure
Final result
A sensor that detects liquid but sends the alarm to the wrong location has not passed a complete functional test.
15. Test Automatic Isolation Functions
Some systems may include automatic valves or pump shutdown functions.
Where applicable, simulate the approved fault conditions and confirm:
Isolation valve operation
Pump shutdown
Standby pump activation
Alarm transmission
System pressure response
Protection of unaffected racks
Recovery procedure
Automatic isolation should prevent the incident from spreading without creating another cooling failure.
16. Verify Redundancy and Failover
If the system is designed with redundant pumps, CDUs or power supplies, test the failover sequence.
Possible tests include:
Duty pump failure
Standby pump activation
CDU power interruption
Communication failure
Sensor failure
Control-system restart
Loss of one cooling branch
Record whether:
Cooling continues
Alarms activate correctly
Flow remains sufficient
Temperature remains controlled
Manual intervention is required
A standby unit that has never been tested should not be assumed to operate during an actual failure.
17. Inspect the System with a Thermal Camera
Carry out a thermal survey under representative load.
Check:
Rack connections
Manifolds
Pumps
Motors
Heat exchangers
Electrical panels
Insulated pipes
Valves and fittings
Look for:
Uneven thermal patterns
Hot connections
Poor insulation
Abnormal motor temperature
Branches with different cooling performance
Unexpected heat near couplings
Thermal imaging should supplement temperature, flow and pressure measurements rather than replace them.
18. Check Pump and Fan Vibration
Measure vibration on the CDU pumps and associated cooling equipment.
Use consistent:
Measurement points
Measurement directions
Instrument settings
Operating speeds
System loads
Record baseline readings during commissioning.
These baseline values can later help maintenance teams identify changes caused by:
Imbalance
Misalignment
Bearing wear
Looseness
Cavitation
Foundation problems
19. Measure Electrical Consumption
Record the power used by:
CDU
Pumps
Chillers
Dry coolers
Cooling-tower fans
Control equipment
Heat-rejection systems
Compare electrical consumption at different IT loads.
A liquid cooling system should be assessed based on overall performance, not only coolant temperature.
Higher pump speeds may improve cooling while increasing energy use. The selected operating point should satisfy both thermal and efficiency requirements.
20. Confirm Data Logging and Time Synchronisation
Temperature, flow, pressure, electrical and control-system data should use aligned timestamps.
This allows engineers to determine:
Which event happened first
How quickly the system reacted
How long the temperature remained high
Whether the alarm was delayed
Whether pump or valve movement corrected the condition
Incorrect timestamps can make a genuine system problem appear unrelated.
Liquid Cooling Commissioning Records
The final commissioning report should include:
System description
Equipment identification
Approved operating limits
Instrument list
Calibration information
Test methods
Measurement results
Alarm test results
Failover test results
Photos and thermal images
Outstanding defects
Corrective actions
Retest results
Final acceptance status
Do not rely only on handwritten readings without identifying the instrument, time, operating condition and measurement location.
Common Liquid Cooling Commissioning Problems
Frequent problems may include:
Incorrect coolant concentration
High conductivity
Unstable pH
Trapped air
Low branch flow
Blocked filters
Reversed flow direction
Incorrect valve positions
Pump cavitation
Delayed temperature response
Leak alarms sent to the wrong destination
Standby equipment not activating
Incomplete calibration records
Finding these issues during commissioning is safer and less expensive than discovering them after critical IT equipment is operating at full load.
Need Instruments for Liquid Cooling Commissioning?
Send MTM Precision:
Required measurement
Expected range
Coolant type
Pipe or connection information
Commissioning application
Quantity
If available, send the system diagram, specification or site photo through WhatsApp.
This allows us to understand whether you require temperature, flow, pressure, coolant quality, thermal imaging, vibration, leak detection or electrical measurement instruments.
MTM Precision supplies industrial testing instruments for data centre commissioning and maintenance in Malaysia, supporting customers in Selangor, Kuala Lumpur, Johor, Penang, Melaka, Negeri Sembilan, Perak, Pahang, Kelantan, Terengganu, Kedah, Perlis, Sabah and Sarawak.
MTM Precision – Data Centre Liquid Cooling Testing Malaysia
Showroom & Service Centre:
No. 29-1 & 29-2, Jalan Bandar 18,
Pusat Bandar Puchong,
47160 Puchong, Selangor, Malaysia.
Tel: 03-8080 7172
WhatsApp: +6016-660 7346
Email: mtmpre@yahoo.com
Website: www.mtmpre.com.my
Send us your measurement requirement + range + coolant type + application photo for liquid cooling commissioning instrument selection in Malaysia.
02 Oct 2026