How to Test Liquid Cooling Response During Changing AI Loads Malaysia
How to Test Liquid Cooling Response During Changing AI Loads Malaysia
A liquid cooling system may maintain acceptable temperatures during a stable IT load but respond poorly when AI servers suddenly increase or reduce power consumption.
For this reason, data centre commissioning should not rely only on steady-state temperature readings.
The test team should also determine:
How quickly does coolant flow respond when the IT load changes?
How high does the temperature rise before the cooling system stabilises?
Can the CDU, pumps and control valves handle repeated load changes?
For AI data centres in Malaysia, dynamic testing can help identify cooling-control problems before the facility begins operating critical high-density workloads.
What Is a Changing AI Load?
AI servers do not always consume the same amount of power.
Power and heat generation may change when:
A training workload begins
More GPUs become active
A workload moves between clusters
Inference demand increases
A scheduled process starts
A job finishes
Equipment enters an idle state
Power-management settings change
A rapid increase in server power creates a rapid increase in heat that must be transferred through:
Processor → Cold Plate → Coolant → CDU → Facility Cooling System
Any delay or restriction along this path may cause temperature overshoot.
Why Steady-State Testing Is Not Enough
A steady-state test checks whether the cooling system can support a stable load after temperatures and flow have settled.
It does not show how the system behaves during the transition.
Two systems may eventually stabilise at the same temperature, but one may respond significantly more slowly.
For example:
System A
Initial return temperature: 34°C
Maximum temperature after load increase: 36°C
Stabilisation time: 45 seconds
System B
Initial return temperature: 34°C
Maximum temperature after load increase: 42°C
Stabilisation time: 4 minutes
Both systems may eventually return to 36°C.
However, System B has a much larger temperature overshoot and slower response.
What Should Be Measured?
A useful dynamic cooling test should measure more than temperature.
Depending on the system, record:
IT power
Rack power
Coolant supply temperature
Coolant return temperature
Coolant flow
Supply pressure
Return pressure
Differential pressure
Pump speed
Control-valve position
CDU electrical consumption
Alarm status
Room temperature and humidity
Relevant component temperatures
The measurements should use synchronised timestamps so the test team can reconstruct the event accurately.
Step 1 – Review the Approved Test Procedure
Before changing the IT load, confirm:
Test objective
Maximum permitted load
Maximum temperature limits
Minimum flow requirement
Alarm thresholds
System redundancy
Emergency stop procedure
Responsible personnel
Required test instruments
Data-recording interval
Do not create uncontrolled loads or simulate failures without approval from the responsible data centre and commissioning teams.
Step 2 – Confirm Instrument Suitability
Check that every measuring instrument has:
Appropriate measuring range
Required accuracy
Suitable response time
Valid calibration or verification status
Sufficient internal memory
Correct date and time
Suitable probes and connections
Reliable battery or external power
A temperature logger that records once every five minutes may be unsuitable for an event lasting less than one minute.
The selected sampling interval should be short enough to capture:
Beginning of the load change
Initial temperature rise
Cooling response
Maximum overshoot
Final stabilisation
Step 3 – Synchronise All Measurement Systems
Synchronise the clocks used by:
IT load system
Power analyser
Temperature logger
Flow meter
Pressure recorder
CDU controller
BMS
DCIM
Test computer
Without time synchronisation, it may be impossible to determine whether the flow increased before or after the temperature alarm.
Record the time difference between systems if exact synchronisation is not possible.
Step 4 – Record the Initial Stable Condition
Before applying a load change, allow the system to reach a stable condition.
Record the baseline:
IT load
Rack power
Supply temperature
Return temperature
Coolant flow
Supply pressure
Return pressure
Pump speed
Valve position
CDU power
Ambient condition
Active alarms
Also record the operating status of:
Duty pump
Standby pump
Chiller or dry cooler
Heat exchanger
Facility-water system
Air-cooling equipment
The baseline provides the reference for evaluating the response.
Step 5 – Apply a Controlled Load Increase
Increase the IT load according to the approved test plan.
Possible test stages may include:
25% load
50% load
75% load
100% approved test load
Alternatively, the project may require a rapid step change, such as:
30% Load → 80% Load
During the test, do not focus only on the final temperature.
Observe the complete sequence:
IT Power Increases
Coolant Return Temperature Begins to Rise
Controller Detects the Change
Pump or Valve Responds
Coolant Flow Changes
Temperature Reaches Its Maximum
System Stabilises
Step 6 – Measure the Response Delay
Identify the time between important events.
Examples include:
Load increase to first temperature change
Load increase to flow increase
Temperature rise to pump-speed change
Alarm limit crossing to BMS notification
Flow increase to temperature recovery
Load change to final stabilisation
The total delay may come from several sources:
Heat transfer through the cold plate
Coolant travel time
Temperature sensor response
Sampling interval
Software filtering
Controller processing
Communication delay
Pump acceleration
Valve movement
Separating these stages helps identify the real cause of slow response.
Step 7 – Record Maximum Temperature Overshoot
Record the highest temperature reached during the transition.
Calculate:
Temperature Overshoot = Maximum Recorded Temperature – Final Stable Temperature
For example:
Maximum temperature: 43°C
Final stable temperature: 38°C
Temperature overshoot: 5°C
Compare the result with:
Equipment limits
Project acceptance criteria
Manufacturer requirements
Previous tests
Other racks or branches
A large overshoot may indicate that the cooling response begins too late or increases too slowly.
Step 8 – Check Coolant Flow Response
Compare coolant flow before, during and after the load change.
Ask:
Did flow increase when required?
How long did the change take?
Did all branches respond equally?
Did flow become unstable?
Possible problems include:
Pump speed not increasing
Valve opening too slowly
Branch flow imbalance
Blocked filter
Restricted cold plate
Air inside the loop
Incorrect controller settings
Inaccurate flow sensor
A stable main-loop flow does not guarantee that every rack receives sufficient coolant.
Step 9 – Monitor Pressure and Differential Pressure
Dynamic load changes may alter pump speed, valve position and coolant flow.
Record:
Supply pressure
Return pressure
Differential pressure across filters
Differential pressure across heat exchangers
Rack manifold differential pressure
Pump differential pressure
Watch for:
Sudden pressure spikes
Unstable pressure
Falling pressure during high load
Excessive differential pressure
Repeated pressure oscillation
Pressure changes can reveal restrictions or control instability that temperature measurement alone may not show.
Step 10 – Observe Pump and Valve Behaviour
Record how the mechanical equipment responds.
Check:
Pump-speed increase
Valve opening
Control signal
Motor current
Pump vibration
Abnormal noise
Cavitation
Repeated hunting or oscillation
A system that repeatedly increases and decreases pump speed may have poor control tuning or unstable sensor feedback.
Pump vibration should be checked under both low-load and high-load conditions.
Step 11 – Check Alarm Performance
Confirm whether alarms activate at the correct stage.
Possible alarms include:
High coolant temperature
High-high coolant temperature
Low flow
Low pressure
High differential pressure
Pump failure
Leak detection
Sensor failure
Communication failure
Record:
Time the condition begins
Time the threshold is crossed
Time the local alarm appears
Time the BMS or DCIM receives the alarm
Alarm description
Notification destination
Required reset procedure
An alarm that activates only after the system has already recovered may require investigation.
Step 12 – Test Load Reduction
Cooling systems must also respond correctly when the IT load drops.
A rapid load reduction may cause:
Excessive coolant flow
Overcooling
Unnecessary pump energy use
Repeated valve movement
Control instability
Condensation risk in certain conditions
Record how quickly the pump, valve and cooling output reduce after the load falls.
The system should maintain acceptable thermal conditions without continuing to consume unnecessary cooling energy.
Step 13 – Repeat the Test
One successful test does not confirm repeatability.
Repeat the approved load-change sequence to determine whether the system behaves consistently.
Compare:
Maximum temperature
Stabilisation time
Flow response
Pressure response
Pump speed
Alarm timing
Electrical consumption
Large differences between repeated tests may indicate unstable control, trapped air, sensor problems or changing operating conditions.
Step 14 – Test Different Racks or Branches
Do not assume that one rack represents the entire system.
Differences may exist due to:
Pipe length
Manifold layout
Valve position
Rack elevation
Cold-plate restriction
Hose routing
IT equipment type
Heat load
Compare the response of critical racks and branches.
A system-wide average can hide a local cooling problem.
Step 15 – Test Redundancy Under Load
Where the approved commissioning procedure requires it, test the failure or isolation of:
Duty pump
One CDU
One cooling branch
One power supply
One communication path
One facility-water component
Confirm whether:
Standby equipment starts
Coolant flow remains sufficient
Temperature remains within limits
Alarms activate correctly
Unaffected racks continue operating
Manual intervention is required
Redundancy should be demonstrated under representative load, not assumed from the equipment list.
How to Analyse the Recorded Data
Plot the measurements on the same time scale.
Useful trends include:
IT Power vs Return Temperature
IT Power vs Coolant Flow
Temperature vs Pump Speed
Flow vs Differential Pressure
CDU Power vs IT Load
Alarm Time vs Actual Event Time
Look for:
Long response delay
High temperature overshoot
Flow instability
Pressure oscillation
Slow recovery
Excessive pump energy
Differences between racks
Delayed alarms
The objective is to understand the relationship between the IT workload and the complete cooling response.
Common Problems Found During Dynamic Testing
Dynamic tests may reveal problems that do not appear during normal spot checks.
Examples include:
Slow temperature sensor
Incorrect sensor placement
Long data-logging interval
Excessive software filtering
Delayed BMS communication
Poor PID tuning
Slow control valve
Insufficient pump capacity
Blocked filter
Air trapped in the loop
Branch flow imbalance
Excessive temperature overshoot
Alarm threshold set too high
Poor failover response
Each problem should be corrected and retested before final acceptance.
Recommended Test Records
The test report should include:
Test objective
System description
IT load profile
Instrument list
Instrument calibration information
Sampling intervals
Sensor locations
Baseline measurements
Load-change sequence
Maximum temperature
Temperature overshoot
Flow and pressure response
Stabilisation time
Alarm timing
Pump and valve response
Electrical consumption
Problems identified
Corrective actions
Retest results
Photos and system diagrams should be included where they help identify measurement locations.
Which Instruments May Be Required?
Depending on the cooling system, the test team may require:
Multi-channel temperature data logger
Fast-response temperature probes
Flow meter
Pressure meter
Differential pressure meter
Power analyser
Clamp meter
Thermal imaging camera
Vibration meter
Leak detection test equipment
Instrument selection should be based on the actual range, response time and data-logging requirement.
Need Help Selecting Instruments for Dynamic Cooling Tests?
Send MTM Precision:
Required measurement
Expected range
Sampling interval
Coolant type
System application
Quantity
If possible, send a system diagram, test specification, trend graph or site photo through WhatsApp.
This allows us to understand whether the requirement involves temperature response, coolant flow, pressure, pump behaviour, power consumption or alarm timing.
MTM Precision supplies industrial testing instruments for data centre commissioning and maintenance in Malaysia, supporting customers in Selangor, Kuala Lumpur, Johor, Penang, Melaka, Negeri Sembilan, Perak, Pahang, Kelantan, Terengganu, Kedah, Perlis, Sabah and Sarawak.
MTM Precision – AI Data Centre Cooling Test Instruments Malaysia
Showroom & Service Centre:
No. 29-1 & 29-2, Jalan Bandar 18,
Pusat Bandar Puchong,
47160 Puchong, Selangor, Malaysia.
Tel: 03-8080 7172
WhatsApp: +6016-660 7346
Email: mtmpre@yahoo.com
Website: www.mtmpre.com.my
Send us your measurement requirement + range + sampling interval + application photo for AI data centre cooling test instrument selection in Malaysia.
02 Oct 2026