How to Use CAD Stakeout with TOKNAV RTK in Malaysia

How to Use CAD Stakeout with TOKNAV RTK in Malaysia

CAD stakeout allows surveyors and construction teams to transfer design information from a digital drawing directly to the project site.

Using TOKNAV tSurvey software with a compatible T50 or T10 Pro GNSS RTK receiver, operators can select points and linework from a supported CAD drawing and navigate to their intended field positions.

This can reduce manual coordinate entry for building, road, drainage, utility and infrastructure projects in Malaysia.

What Is CAD Stakeout?

Traditional point stakeout requires the operator to enter or import a list of coordinates.

CAD stakeout uses design information from a drawing. Depending on the available software functions and file, the operator may select:

  • Points

  • Line endpoints

  • Intersections

  • Corners

  • Alignments

  • Arcs

  • Building grids

  • Other supported drawing features

The software then provides directional and distance guidance to the selected position.

Compatible TOKNAV Software

Both TOKNAV software versions document CAD-related functions.

tSurvey 1.0

Includes conventional engineering workflows such as:

  • CAD stakeout

  • Point and line stakeout

  • Road stakeout

  • Project management

  • Coordinate-system setup

  • Import and export

tSurvey 2.0

Provides a broader workflow that includes:

  • CAD

  • Point, line and polygon functions

  • Road stakeout

  • AR stakeout

  • Laser measurement

  • LandXML

  • GIS formats

  • Google Maps

  • WMS/WFS

For conventional T10 Pro construction work, tSurvey 1.0 may be sufficient. For T50 AR and laser workflows, tSurvey 2.0 is the more appropriate option.

Compatible RTK Receivers

TOKNAV T10 Pro

Suitable for:

  • General construction stakeout

  • Building grids

  • Road and drainage work

  • Control points

  • Topographic survey

  • Infrastructure projects

TOKNAV T50

Provides the same published RTK accuracy while adding:

  • 100m green laser

  • AR stakeout

  • Inaccessible-point measurement

  • IMU tilt measurement

Both can be paired with the TOKNAV TBase or a compatible network correction service.

Step 1: Prepare the CAD Drawing

Before transferring the file, clean the drawing in the office.

Remove unnecessary items such as:

  • Title blocks

  • Notes

  • Hatching

  • Unused layers

  • Duplicate linework

  • External references

  • Decorative objects

  • Irrelevant project areas

A simplified drawing is easier to navigate on a field controller.

Keep only the layers and features required for the survey or setting-out task.

Step 2: Confirm Drawing Units

Check whether the drawing uses:

  • Metres

  • Millimetres

  • Feet

  • Another project unit

A drawing prepared in millimetres but imported as metres can appear at the wrong scale.

Confirm the distance between two known points before using the drawing in the field.

Step 3: Check the Coordinate System

The CAD drawing and RTK project must use matching coordinates.

Confirm:

  • Datum

  • Projection

  • Coordinate zone

  • Local grid

  • False easting and northing

  • Scale factor

  • Rotation

  • Geoid model

  • Elevation reference

  • Site-calibration parameters

A drawing can appear correctly shaped while being shifted or rotated relative to the physical site.

Step 4: Confirm the Drawing Origin

Some architectural or engineering drawings use an arbitrary origin instead of real survey coordinates.

For example, a building corner may be assigned:

  • E = 0

  • N = 0

The GNSS receiver, however, measures positions within the selected geographical or project coordinate system.

The drawing may require localization or transformation using verified common points before GNSS stakeout is possible.

Step 5: Export a Supported File

Export the cleaned drawing in a format supported by the supplied tSurvey version.

Before leaving the office:

  1. Save the original drawing separately.

  2. Create a simplified field copy.

  3. Confirm the required file version.

  4. Use clear layer names.

  5. Check all units.

  6. Retain several known control points.

  7. Transfer the file to the controller.

Because CAD format support can vary by software version, test a sample file before the project begins.

Step 6: Create the tSurvey Project

On the controller:

  • Create or open the project

  • Select the correct coordinate system

  • Enter localization parameters if required

  • Confirm distance and elevation units

  • Connect to the TOKNAV receiver

  • Select the correction method

  • Import the CAD file

Review the drawing on the controller and confirm that it appears at the expected coordinates.

Step 7: Connect the RTK System

The Rover must receive valid correction data from:

  • TOKNAV TBase through UHF radio

  • A compatible CORS service

  • A VRS or NTRIP connection

  • Another supported correction source

Confirm:

  • Satellite tracking

  • Correction-data age

  • RTK fixed status

  • Base identification

  • Radio or network connection

  • Correct pole height

  • IMU initialization, if used

Do not begin critical stakeout with a Float or Single solution.

Step 8: Verify the Project on a Known Point

Before staking any design features:

  1. Measure an independent known point.

  2. Compare the measured coordinate with the accepted value.

  3. Check horizontal and vertical differences.

  4. Confirm that the drawing aligns with physical site features.

  5. Investigate any unexpected discrepancy.

This check helps detect incorrect Base coordinates, units, drawing origin or coordinate-system settings.

Step 9: Select the CAD Feature

Choose the required point, endpoint, intersection or supported line feature.

Confirm:

  • Layer

  • Point or feature identity

  • Drawing revision

  • Design elevation

  • Required offset

  • Construction description

On drawings with dense linework, zoom in and verify that the correct object has been selected.

Step 10: Stake Out the Position

Follow the displayed guidance toward the selected coordinate.

The software may show:

  • Direction

  • Distance

  • Left or right movement

  • Forward or backward movement

  • Cut or fill

  • Current coordinate

  • Target coordinate

For the TOKNAV T50, AR guidance may help the operator approach the target visually before completing the final precise positioning.

Step 11: Mark and Record the Point

Once the position is within the required tolerance:

  • Mark the point

  • Record the stakeout result

  • Add a code or note

  • Take an as-built measurement where required

  • Photograph the mark if part of the site procedure

  • Record any offset used

  • Identify the drawing revision

Important structural points should be checked independently.

Common CAD Stakeout Errors

Wrong Drawing Revision

An outdated drawing can cause correctly measured points to be placed at superseded design positions.

Incorrect Units

A metre/millimetre mismatch creates a major scale error.

Arbitrary Drawing Origin

The drawing may not use actual project coordinates.

Incorrect Transformation

Poorly selected common points can shift, rotate or distort the drawing.

Wrong Base Coordinates

Every Rover result may be shifted even when the RTK solution shows Fixed.

Selecting the Wrong Feature

Dense drawings can contain overlapping points, lines and layers.

Ignoring Elevation

A correct horizontal point may still have an incorrect design level.

No Known-Point Verification

A simple independent check could identify the problem before multiple points are marked.

CAD Stakeout with T10 Pro or T50?

Choose the T10 Pro when:

  • Conventional CAD stakeout is the main task

  • Design points are accessible

  • AR and laser functions are unnecessary

  • Lower initial cost is important

Choose the T50 when:

  • AR guidance is useful

  • The site contains difficult-to-reach points

  • Laser measurement is required

  • The receiver will handle varied construction workflows

Both models provide the same published RTK horizontal and vertical accuracy.

Information to Confirm Before Buying

Confirm:

  • Exact tSurvey version

  • Permanent software licence

  • Supported CAD formats and versions

  • T50 AR and laser activation

  • Controller model

  • Malaysia activation

  • Coordinate-system support

  • Data import and export requirements

  • Software updates

  • Training and technical support

TOKNAV CAD Stakeout System Supplier in Malaysia

Contact MTM Precision for the TOKNAV T50, T10 Pro, TBase and tSurvey software, including CAD stakeout configuration, quotation, demonstration and technical discussion in Malaysia.

MTM Precision Sdn. Bhd. (744811-A)

Telephone: +603-8080 7172
WhatsApp: +6016-660 7346
Email: mtmpre@yahoo.com / enquiry@mtmpre.com.my
Website: www.mtmpre.com.my

Showroom & Service Centre:
No. 29-1 & 29-2, Jalan Bandar 18,
Pusat Bandar Puchong,
47160 Puchong, Selangor, Malaysia.

18 Sep 2026