During PLC commissioning, not every field sensor or transmitter may be ready when the automation engineer needs to test the control system.
A pressure transmitter may not yet be installed.
A tank may still be empty.
The flow system may not be operating.
The production machine may not yet be running.
But the engineer may still need to check whether the PLC analog input, HMI display, scaling and alarm logic are working correctly.
The FNIRSI SG-003A Signal Generator can provide known electrical test signals for suitable commissioning applications.
For system integrators, automation engineers, panel builders and factory maintenance teams in Malaysia, this can be useful when testing PLC systems before the actual process is fully operational.
Why Is Signal Simulation Useful During PLC Commissioning?
Consider a new factory control system.
The PLC panel has already been installed, but several field instruments are not ready.
The system may eventually receive signals from:
Pressure transmitters
Temperature transmitters
Flow transmitters
Level transmitters
Process sensors
Many of these instruments may use a 4-20 mA signal.
Instead of waiting until every transmitter and process is operational, the commissioning engineer can test suitable parts of the control system using known signals.
What Can You Check?
Signal simulation can help technicians check suitable functions such as:
PLC analog input response
PLC channel assignment
Engineering-unit scaling
HMI display
Alarm thresholds
Trend response
Control logic
Input mapping
This allows many control-system problems to be identified before the plant starts normal operation.
Example: Testing a Pressure Input
Suppose a PLC analog input will eventually receive a pressure transmitter with this range:
0-10 bar = 4-20 mA
During commissioning, the actual pressure transmitter is not yet installed.
The engineer can check suitable points such as:
4 mA = 0 bar
8 mA = 2.5 bar
12 mA = 5 bar
16 mA = 7.5 bar
20 mA = 10 bar
If the HMI displays these values correctly, the PLC scaling is responding as expected.
If not, the engineer can investigate the configuration before the field transmitter is connected.
Example: Testing a Tank Level Display
Consider a water tank level system configured as:
4-20 mA = 0-100%
The tank has not yet been filled.
However, the automation engineer wants to check the HMI display.
Suitable test points may include:
4 mA = 0%
8 mA = 25%
12 mA = 50%
16 mA = 75%
20 mA = 100%
By changing the test signal, the engineer can check whether the displayed level follows the expected value.
This means the basic PLC and HMI configuration can be checked without physically filling and emptying the tank.
Check PLC Scaling Before Startup
Incorrect scaling is a common source of commissioning problems.
For example, the transmitter specification may be:
0-16 bar = 4-20 mA
but the PLC program may accidentally be configured for:
0-10 bar = 4-20 mA
At 4 mA, both configurations may show zero.
At 20 mA, however, the incorrect configuration becomes obvious.
Testing several points across the range can help identify this type of mistake.
Why Test More Than 4 mA and 20 mA?
Checking only the minimum and maximum values may not reveal every configuration problem.
A useful functional check may include:
4 mA
8 mA
12 mA
16 mA
20 mA
This provides five points across the range.
For a linear system, the displayed process value should change proportionally.
If the endpoints are correct but intermediate values are not, the scaling or PLC logic should be investigated.
Testing the HMI
A PLC input may be configured correctly while the HMI display is wrong.
For example:
The PLC internal value represents 50%.
But the HMI displays 500%.
This may be caused by:
Incorrect HMI scaling
Wrong tag configuration
Decimal-point settings
Engineering-unit configuration
Incorrect data mapping
A known test signal provides a predictable reference value that can help identify these errors.
Testing High and Low Alarms
Suppose a pressure system has:
Low Pressure Alarm = 2 bar
High Pressure Alarm = 8 bar
and the measurement range is:
0-10 bar = 4-20 mA
During suitable commissioning work, known signals can be used to check how the control system responds around these thresholds.
The engineer can observe:
Alarm indication
HMI warning
PLC status
Event recording
Control response
However, extra care is required if an alarm is connected to automatic machinery or shutdown logic.
Testing a High-Level Alarm
Consider a tank system configured as:
4-20 mA = 0-100%
The high-level alarm is programmed at 90%.
A commissioning engineer may need to verify whether the PLC and HMI respond when the simulated level approaches and crosses the alarm threshold.
This can be much easier than physically filling the tank simply to test the alarm display.
But the engineer must first determine whether the signal can activate:
Pumps
Valves
Sirens
Interlocks
Emergency shutdown logic
Signal simulation should only be performed under an approved commissioning procedure.
Testing Multiple Analog Input Channels
A new PLC panel may contain many analog inputs.
For example:
AI01 - Pressure
AI02 - Temperature
AI03 - Flow
AI04 - Tank Level
AI05 - Pressure
AI06 - Flow
During commissioning, the engineer needs to confirm that every field cable and PLC channel corresponds to the correct HMI tag.
Applying a known test signal to each appropriate channel can help verify:
Correct channel
Correct HMI tag
Correct engineering unit
Correct scaling
This can help identify crossed wires or incorrect tag assignments.
Example: Wrong PLC Channel
Imagine a known signal is applied to the pressure input.
Instead of the pressure value changing on the HMI, the tank level changes.
This immediately suggests a problem with:
Channel assignment
Wiring
PLC mapping
or
HMI tag configuration
Without a controlled test signal, this type of mistake may be more difficult to identify.
FNIRSI SG-003A for Panel Builders
Panel builders can also benefit from signal simulation.
Before a control panel is delivered to the customer site, suitable analog input functions may be checked during panel testing.
For example:
Apply known signal
Confirm PLC receives the input
Check programmed scaling
Check HMI indication
Verify channel identification
This can help identify configuration problems before installation.
FNIRSI SG-003A for System Integrators
System integrators frequently work on projects where mechanical, electrical and instrumentation installation progress at different speeds.
The PLC software may be ready before the actual process equipment.
A portable signal generator can allow suitable software and input testing to continue while waiting for field instrumentation.
Potential applications include:
PLC commissioning
HMI testing
Analog input testing
Signal simulation
Control-panel testing
Instrumentation troubleshooting
Factory acceptance testing support
Site commissioning
The exact test method depends on the system design and project requirements.
Factory Acceptance Testing
During suitable Factory Acceptance Testing (FAT), a control panel may need to demonstrate that analog inputs and displays respond correctly.
Known signals can help simulate different process conditions.
For example:
Low pressure
Normal pressure
High pressure
Empty tank
Half-full tank
Full tank
This allows the customer and system integrator to observe how the PLC and HMI respond before the system reaches the actual site.
Whether a particular instrument is appropriate for formal FAT documentation depends on the project requirements.
Site Acceptance Testing
Similar techniques may be useful during Site Acceptance Testing (SAT).
However, site testing requires additional attention because the control system may already be connected to real equipment.
Before injecting a simulated signal, determine whether it could cause:
Motor operation
Pump startup
Valve movement
Alarm activation
Process changes
Safety-system response
The system should be placed in the appropriate test or isolated condition before signal simulation.
Signal Simulation Does Not Replace Full Commissioning
The FNIRSI SG-003A can help test suitable electrical and control-system functions.
It does not replace complete commissioning.
A full commissioning process may also require:
Sensor verification
Transmitter configuration
Mechanical checks
Process testing
Interlock testing
Safety-system verification
Loop checking
Calibration
Signal simulation is one useful part of a larger commissioning process.
Important Before Connecting the SG-003A
Before applying any test signal:
Check the PLC input specification
Confirm current or voltage mode
Check the correct terminals
Confirm polarity
Understand the loop power arrangement
Verify the expected signal range
Check what equipment is controlled by the input
Follow the approved commissioning procedure
Never inject a test signal into an operating system without understanding the consequences.
Looking for FNIRSI SG-003A for PLC Commissioning in Malaysia?
MTM Precision Sdn Bhd supplies the FNIRSI SG-003A Signal Generator in Malaysia for PLC commissioning, industrial automation, control-panel testing and factory maintenance applications.
If you are working on a PLC project and are unsure whether the SG-003A is suitable, send us a photo of the PLC analog input module, transmitter specification, control panel or wiring diagram through WhatsApp.
We can help evaluate the application before you purchase.
MTM Precision Sdn Bhd
Showroom & Service Centre
No 29-1 & 2, Jalan Bandar 18,
Pusat Bandar Puchong,
47160 Puchong, Selangor, Malaysia
Tel: 03-8080 7172
WhatsApp: +6016-660 7346
Email: mtmpre@yahoo.com
Website: www.mtmpre.com.my
Serving customers across Selangor, Kuala Lumpur, Johor, Penang, Melaka, Negeri Sembilan, Perak, Pahang, Kelantan, Terengganu, Kedah, Perlis, Sabah and Sarawak.
04 Oct 2026