How to Perform a 4-20 mA Loop Check with FNIRSI SG-003A Malaysia
How to Perform a 4-20 mA Loop Check with FNIRSI SG-003A Malaysia
A 4-20 mA loop check is an important part of industrial instrumentation, commissioning and troubleshooting.
The objective is not simply to see whether there is current in the wire.
A proper functional loop check helps confirm that a signal can travel through the expected control-system path and produce the correct response.
For example:
Transmitter > Field Wiring > PLC > HMI
For suitable applications, the FNIRSI SG-003A Signal Generator can provide known test signals to help technicians check how the receiving side of a 4-20 mA loop responds.
For instrumentation technicians, automation engineers, system integrators and factory maintenance teams in Malaysia, this can be useful during commissioning and troubleshooting.
What Is a 4-20 mA Loop?
A 4-20 mA current loop is commonly used to transmit industrial process measurements.
Examples include:
Pressure
Temperature
Flow
Level
Position
Other process variables
A typical linear relationship is:
4 mA = 0%
8 mA = 25%
12 mA = 50%
16 mA = 75%
20 mA = 100%
The actual engineering values depend on the transmitter configuration.
Example: Pressure Loop
Suppose a pressure transmitter is configured as:
0-10 bar = 4-20 mA
The expected values are:
4 mA = 0 bar
8 mA = 2.5 bar
12 mA = 5 bar
16 mA = 7.5 bar
20 mA = 10 bar
During a functional loop check, the technician can determine whether known signals produce the expected values at the PLC and HMI.
Why Perform a Loop Check?
A system may be wired completely but still contain problems.
Examples include:
Wrong field cable
Wrong PLC channel
Reversed polarity
Incorrect terminal
Wrong PLC scaling
Incorrect HMI tag
Incorrect engineering range
Configuration errors
A loop check helps identify these problems before normal operation.
When Should You Perform a Loop Check?
Loop checks may be useful during:
New control-panel installation
PLC commissioning
New transmitter installation
Factory expansion
Control-system modification
Shutdown maintenance
Transmitter replacement
Troubleshooting
They may also form part of FAT or SAT activities depending on the project procedure.
Step 1: Understand the Loop
Before connecting test equipment, understand the complete signal path.
For example:
Pressure Transmitter > Junction Box > Control Panel > PLC AI03 > PLC Program > HMI Pressure Tag
Write down or verify each stage.
This is important because the purpose of a loop check is to confirm that the correct signal reaches the correct destination.
Step 2: Confirm the Signal Type
Do not assume every analog loop is 4-20 mA.
Check the instrument and PLC specifications.
The system may use:
4-20 mA
0-20 mA
0-10 V
or another signal type.
Confirm the exact signal before connecting the SG-003A or other test equipment.
Step 3: Confirm the Engineering Range
Suppose the transmitter is labelled:
0-16 bar = 4-20 mA
Then your expected values are:
4 mA = 0 bar
8 mA = 4 bar
12 mA = 8 bar
16 mA = 12 bar
20 mA = 16 bar
If the PLC is accidentally configured for 0-10 bar, the loop may electrically work while the displayed value remains incorrect.
Step 4: Identify the Correct PLC Channel
Confirm which analog input channel receives the signal.
For example:
AI01 - Flow
AI02 - Level
AI03 - Pressure
AI04 - Temperature
If you test AI03 but the HMI value associated with AI04 changes, there may be a channel assignment or tag problem.
This is exactly the type of issue that loop checking can reveal.
Step 5: Place the System in a Safe Test Condition
This step is critical.
A simulated analog signal can affect control logic.
Changing a signal may cause:
Pump startup
Motor operation
Valve movement
Alarm activation
Interlock activation
Automatic sequence changes
Shutdown functions
Before injecting any test signal, follow the site's approved isolation and commissioning procedure.
Step 6: Apply the Lower Test Point
For a standard 4-20 mA system, a useful starting point is:
4 mA
For a 0-100% range, the expected result is:
0%
For a 0-10 bar pressure range:
0 bar
Check the PLC and HMI.
Record the result if required by the commissioning procedure.
Step 7: Apply the Midpoint
Next, apply:
12 mA
For a standard linear 0-100% range:
12 mA = 50%
For:
0-10 bar
the expected value is:
5 bar
This midpoint is particularly useful because it can reveal scaling problems that are not obvious at the lower endpoint.
Step 8: Apply the Upper Test Point
Next, check:
20 mA
For a 0-100% range:
20 mA = 100%
For:
0-10 bar
the expected result is:
10 bar
If the HMI instead displays 16 bar, investigate the configured engineering range.
Should You Check 5 Points?
For troubleshooting and commissioning, additional test points can provide more information.
A common functional sequence is:
4 mA = 0%
8 mA = 25%
12 mA = 50%
16 mA = 75%
20 mA = 100%
This helps verify that the system responds across the range rather than only at the endpoints.
The exact number of test points should follow your project or maintenance procedure.
Example: Level Transmitter Loop Check
Suppose a tank level transmitter is configured as:
0-5 m = 4-20 mA
Expected results are:
4 mA = 0 m
8 mA = 1.25 m
12 mA = 2.5 m
16 mA = 3.75 m
20 mA = 5 m
If all values display correctly, the receiving side is responding as expected to the known signals.
If the HMI shows:
4 mA = 0 m
12 mA = 5 m
20 mA = 10 m
the PLC or HMI may be configured for the wrong range.
Example: Wrong HMI Tag
Imagine you are checking a pressure loop.
You apply a changing test signal to the expected pressure input.
But instead of the pressure display changing, the HMI flow reading changes.
This may indicate:
Incorrect PLC tag
Incorrect HMI tag
Wrong field cable
Wrong analog input channel
The electrical signal may be working perfectly.
The problem is that it is connected or mapped to the wrong place.
Example: PLC Raw Value Changes but HMI Does Not
During the loop check, the PLC programming software shows the raw analog value changing correctly.
However, the HMI remains fixed.
This suggests the issue may be downstream of the physical analog input.
Check:
PLC scaling
HMI tag
Communication
Display configuration
Program logic
This is why it is useful to observe both the PLC and HMI during a loop check.
Example: Nothing Changes
Suppose you apply appropriate known signals but the PLC raw value does not change.
Investigate:
Correct terminals
Correct channel
Input configuration
Current vs voltage mode
Wiring
Loop arrangement
PLC analog input module
Do not immediately conclude that the PLC module is damaged.
Check the configuration and connections first.
Loop Check vs Transmitter Calibration
These are not necessarily the same task.
A functional loop check asks:
Does the control system respond correctly to a known signal?
Transmitter calibration asks questions such as:
Does the transmitter accurately convert the physical process input into the expected output?
For example, fully calibrating a pressure transmitter may require an appropriate pressure reference and pressure source.
Generating 12 mA alone does not prove that a pressure transmitter correctly measures 5 bar.
The SG-003A should therefore not be treated as a replacement for every physical calibration instrument.
Loop Check vs PLC Analog Input Calibration
Similarly, observing that a PLC displays approximately 50% when a test signal is applied is useful for functional troubleshooting.
Formal calibration may require:
Specified accuracy
Traceable reference equipment
Known uncertainty
Documented procedures
Recorded results
Calibration certificates
The required equipment depends on the purpose of the test.
Why the FNIRSI SG-003A Is Useful for Loop Troubleshooting
For suitable applications, the FNIRSI SG-003A gives technicians a controlled test condition.
Instead of relying entirely on the process transmitter, technicians can introduce a known supported signal and observe the receiving system.
This can help isolate problems involving:
PLC inputs
Scaling
HMI displays
Channel assignments
Control-panel wiring
Automation configuration
A Practical Troubleshooting Sequence
When a 4-20 mA loop is not working correctly, a systematic sequence is better than replacing components randomly.
Check:
1. What is the expected signal?
2. What is the transmitter range?
3. Is the transmitter powered correctly?
4. Is the wiring correct?
5. What signal is actually present?
6. Is the PLC configured for the correct input type?
7. Does the PLC respond to a known signal?
8. Is the scaling correct?
9. Does the HMI display the PLC value correctly?
This approach can significantly reduce troubleshooting time.
Applications in Malaysian Industry
4-20 mA loops are used across many industrial environments.
Potential applications include:
Manufacturing plants
Water and wastewater systems
Pump systems
HVAC plants
Boilers and chillers
Chemical processes
Food and beverage production
Building services
Process plants
Factory automation
For maintenance teams working with these systems, signal simulation can be a useful troubleshooting capability.
Important Safety Reminder
Before performing a loop check:
Review the wiring diagram
Confirm the correct signal type
Check the input terminals
Check polarity
Understand the loop power arrangement
Verify the allowed signal range
Identify any automatic control actions
Follow site isolation and safety procedures
Never inject a signal into an operating control system without understanding what the PLC may do with that signal.
Looking for FNIRSI SG-003A for 4-20 mA Loop Checking in Malaysia?
MTM Precision Sdn Bhd supplies the FNIRSI SG-003A Signal Generator in Malaysia for 4-20 mA troubleshooting, PLC testing, control-panel commissioning and industrial automation applications.
If you need to perform a 4-20 mA loop check and are unsure whether the SG-003A is suitable, send us a photo of your transmitter, PLC analog input module, wiring terminals or loop diagram through WhatsApp.
We can help evaluate your application before you purchase.
MTM Precision Sdn Bhd
Showroom & Service Centre
No 29-1 & 2, Jalan Bandar 18,
Pusat Bandar Puchong,
47160 Puchong, Selangor, Malaysia
Tel: 03-8080 7172
WhatsApp: +6016-660 7346
Email: mtmpre@yahoo.com
Website: www.mtmpre.com.my
Serving customers across Selangor, Kuala Lumpur, Johor, Penang, Melaka, Negeri Sembilan, Perak, Pahang, Kelantan, Terengganu, Kedah, Perlis, Sabah and Sarawak.
04 Oct 2026