How to Perform Anchor Pull-Out Test Using Langry APT200 Malaysia

How to Perform Anchor Pull-Out Test Using Langry APT200 Malaysia

 

Anchor Pull-Out Testing Procedure with Langry APT200

 

The Langry APT200 Anchor Pull-Out Tester is a professional hydraulic testing instrument designed to apply controlled tensile loads to installed anchors, anchor rods, steel bars, expansion bolts and other suitable anchoring components.

 

With a maximum measurement range of 200kN, the APT200 is commonly referred to as a 20-ton class anchor pull-out tester and is suitable for construction inspection, civil engineering, façade works and QA/QC applications in Malaysia.

 

This guide provides a general overview of how an anchor pull-out test may be performed using the Langry APT200.

 

The exact test procedure, proof load, acceptance criteria, loading rate and test duration should always follow the relevant project specification, approved test method and engineer's requirements.

 

What Is an Anchor Pull-Out Test?

 

An anchor pull-out test applies a controlled tensile force to an installed anchor.

 

The purpose is to evaluate how the installed anchoring system behaves when subjected to the specified tensile load.

 

Depending on the project, testing may be performed as a:

 

Proof test

 

Quality control test

 

Installation verification test

 

Site investigation

 

Comparative test

 

Ultimate load test

 

It is important to establish the purpose of the test before starting because the required loading procedure and acceptance criteria can be different.

 

Equipment Required for Anchor Pull-Out Testing

 

A typical test setup may include:

 

Langry APT200 Anchor Pull-Out Tester

 

Hydraulic cylinder

 

Digital force indicator

 

Hydraulic pump

 

Pull rod

 

Suitable adapter or converter

 

Appropriate support or reaction arrangement

 

Anchor under test

 

Project test documentation

 

Appropriate personal protective equipment

 

The exact accessories required depend on the anchor type, diameter, geometry and test arrangement.

 

Langry APT200 Basic Specifications

 

SpecificationLangry APT200Measurement Range0–200kNCapacity ClassApprox. 20 TonCylinder Center Hole35mmCylinder Stroke70mmCylinder WeightApprox. 13kgCommon AnchorageΦ6–Φ25Pull RodM24ConverterM6–M22Data Storage500 RecordsContinuous Working Time>200 HoursAccuracy ClassificationEN ISO 7500-1 Class 1

 

Step 1 – Identify the Anchor to Be Tested

 

Before setting up the equipment, identify the anchor and record the relevant information.

 

This may include:

 

Anchor type

 

Anchor manufacturer

 

Anchor diameter

 

Anchor length

 

Embedment depth

 

Base material

 

Installation location

 

Installation date

 

Required test load

 

Project reference

 

The operator should also confirm whether the test is intended to verify a specified proof load or determine another performance characteristic.

 

Step 2 – Inspect the Test Area

 

Inspect the anchor and surrounding substrate before installing the pull-out tester.

 

Look for obvious conditions such as:

 

Cracked concrete

 

Damaged anchor

 

Loose fixing

 

Irregular surface

 

Insufficient exposed thread or rod

 

Obstructions around the anchor

 

Edge proximity

 

Existing substrate damage

 

Any unusual condition should be recorded before testing.

 

This is important because the condition of the surrounding material can influence the test setup and interpretation of results.

 

Step 3 – Select the Correct Adapter

 

The connection between the pull-out tester and the anchor must be suitable for the anchor being tested.

 

The Langry APT200 uses an M24 pull rod with converters covering suitable configurations from M6 to M22.

 

Select an appropriate adapter according to the anchor size and test arrangement.

 

The connection should be secure and properly aligned before applying load.

 

Step 4 – Position the Hydraulic Cylinder

 

Place the hydraulic cylinder over the anchor and arrange the pulling system according to the required test configuration.

 

Correct positioning is important.

 

The pulling force should be applied as concentrically as practical to avoid introducing unnecessary side loading or bending.

 

The reaction surface should also be suitable for the test.

 

An incorrect reaction arrangement may affect the measured result or damage the surrounding substrate.

 

Step 5 – Connect the Pulling Assembly

 

Connect the pull rod, adapter and anchor securely.

 

Before applying significant pressure, check that:

 

Connections are properly engaged

 

Pull rod is correctly positioned

 

Hydraulic cylinder is stable

 

Reaction arrangement is stable

 

Test equipment is aligned

 

Hydraulic components are correctly connected

 

Personnel are clear of the potential failure path

 

Never begin a high-load pull test with a loose or poorly aligned setup.

 

Step 6 – Zero the Digital Indicator

 

Before starting the measurement, switch on the digital force indicator and confirm that the reading is correctly zeroed according to the equipment operating procedure.

 

This provides a clear starting reference before the tensile load is applied.

 

Step 7 – Apply the Load Gradually

 

Operate the hydraulic pump to increase the tensile load.

 

The load should be applied according to the approved testing procedure.

 

Avoid uncontrolled or sudden loading.

 

Depending on the project specification, the test may require:

 

Progressive loading

 

Specific loading stages

 

A defined proof load

 

Holding the load for a specified period

 

Recording readings at different load levels

 

Do not assume that every anchor should be tested to the maximum 200kN capacity of the APT200.

 

The required test load is determined by the anchor system and project requirements—not by the maximum capacity of the tester.

 

Step 8 – Monitor the Applied Force

 

Observe the digital display as the load increases.

 

The operator should monitor the test continuously and look for abnormal behaviour.

 

Depending on the test objective, observations may include:

 

Applied tensile load

 

Anchor movement

 

Substrate cracking

 

Anchor slipping

 

Sudden reduction in load

 

Visible deformation

 

Failure of the fixing

 

Condition after holding the specified load

 

If abnormal or unsafe behaviour occurs, loading should be stopped in accordance with the approved test procedure.

 

Step 9 – Hold the Required Test Load

 

Some anchor testing procedures require the specified load to be maintained for a defined period.

 

The required holding time depends on the project specification or approved test method.

 

During this period, the operator should monitor the load and anchor behaviour.

 

A stable reading alone does not automatically mean that an anchor has passed.

 

The result must be assessed against the applicable acceptance criteria.

 

Step 10 – Release the Hydraulic Load

 

After completing the required loading sequence, release the hydraulic pressure in a controlled manner.

 

Do not release the system abruptly.

 

Once the load has returned to a safe level, the pulling assembly and hydraulic cylinder can be removed.

 

Step 11 – Inspect the Anchor After Testing

 

Inspect the anchor and surrounding substrate again after the test.

 

Look for:

 

Permanent movement

 

Anchor deformation

 

Concrete cracking

 

Pull-out

 

Surface damage

 

Thread damage

 

Other visible changes

 

Post-test observations can provide useful information when preparing the test report.

 

Step 12 – Record the Test Result

 

The Langry APT series supports storage of up to 500 measurement records.

 

However, a complete project record may require more information than the force reading alone.

 

A typical anchor pull-out test record may include:

 

Project name

 

Test location

 

Anchor identification

 

Anchor type

 

Anchor diameter

 

Base material

 

Test date

 

Test equipment

 

Required test load

 

Maximum applied load

 

Holding time

 

Observations

 

Pass/fail result according to specified criteria

 

Operator information

 

Good documentation is particularly important when multiple anchors are tested across a construction project.

 

What Does a Failed Anchor Pull-Out Test Mean?

 

A failed result does not always have one single cause.

 

Possible factors may include:

 

Incorrect Installation

 

Improper installation can reduce the performance of the anchor.

 

Incorrect Hole Diameter

 

A drilled hole that does not meet the anchor manufacturer's requirements may affect anchorage.

 

Insufficient Embedment

 

An anchor installed with inadequate embedment may not achieve the required performance.

 

Poor Hole Cleaning

 

For some anchoring systems, particularly bonded anchors, hole preparation and cleaning are critical.

 

Weak or Damaged Base Material

 

The condition and strength of the substrate can influence anchor performance.

 

Incorrect Anchor Selection

 

The selected anchor may not be appropriate for the application, substrate or required load.

 

Installation Workmanship

 

Even a correctly specified anchor can perform poorly if installation procedures are not followed.

 

The cause of a failed test should therefore be investigated rather than assuming that the anchor product itself is defective.

 

Proof Testing vs Pulling an Anchor to Failure

 

These two approaches should not be confused.

 

Proof Testing

 

A proof test normally applies a predetermined load to verify the installed anchor against specified project requirements without intentionally loading it to destruction.

 

Ultimate or Failure Testing

 

A test intended to investigate ultimate performance continues according to a defined procedure until a failure criterion is reached.

 

The appropriate method depends on the engineering objective.

 

For actual construction projects, always follow the engineer's approved testing procedure and acceptance criteria.

 

Important Safety Considerations

 

Anchor pull-out testing can involve substantial forces.

 

A 200kN tester is capable of generating very high tensile loads.

 

Operators should therefore:

 

Use appropriate PPE

 

Inspect equipment before testing

 

Use suitable adapters

 

Confirm secure connections

 

Maintain proper alignment

 

Keep unnecessary personnel away

 

Avoid standing in the potential failure path

 

Never exceed equipment limits

 

Follow the manufacturer's operating instructions

 

Follow the project's approved testing procedure

 

Anchor, adapter or test fixture failure under high load can create a serious hazard.

 

Common Mistakes During Anchor Pull-Out Testing

 

Some common testing mistakes include:

 

Using the wrong adapter

 

Poor alignment of the tester

 

Applying load too quickly

 

Testing without a defined test load

 

Using an unsuitable reaction arrangement

 

Ignoring substrate condition

 

Failing to record the anchor location

 

Confusing proof testing with destructive testing

 

Assuming tester capacity equals required test load

 

Testing without clear acceptance criteria

 

A professional pull-out test requires both suitable equipment and a properly defined testing procedure.

 

Why Use the Langry APT200?

 

The Langry APT200 provides a useful combination of capacity and portability for professional anchor testing.

 

Its 200kN / approximately 20-ton capacity makes it suitable for a broad range of construction and engineering applications where a lower-capacity pull tester may not provide sufficient range.

 

Typical users include:

 

Construction contractors

 

Civil engineering companies

 

Façade contractors

 

Anchor installation companies

 

QA/QC teams

 

Engineering consultants

 

Inspection companies

 

Testing laboratories

 

Infrastructure contractors

 

Frequently Asked Questions

 

How much force can the Langry APT200 apply?

 

The APT200 has a measurement range of 0–200kN, approximately equivalent to a 20-ton class system.

 

Can I simply test every anchor to 200kN?

 

No. The 200kN figure is the capacity of the tester. The actual test load must follow the anchor specification, approved test method and project engineering requirements.

 

Can the APT200 test expansion bolts?

 

Yes, suitable expansion bolts are among the applications of this type of anchor pull-out tester, provided the correct testing setup and accessories are used.

 

Can it test steel bars?

 

The Langry APT series is designed for pull-out testing applications involving suitable anchor rods, steel bars and other anchoring components.

 

Can the APT200 be used for curtain wall projects?

 

Yes. Anchor pull-out testing can be used in curtain wall and façade anchoring applications. The testing method and acceptance criteria must follow the project requirements.

 

Why is alignment important during pull-out testing?

 

Poor alignment may introduce bending or side loading instead of applying a predominantly axial tensile force, potentially affecting the test and creating an unsafe setup.

 

Where can I get a Langry APT200 Anchor Pull-Out Tester in Malaysia?

 

MTM Precision Sdn. Bhd. supplies construction testing and measurement equipment in Malaysia and can assist customers with selecting a suitable Langry anchor pull-out tester for their required test range and application.

 

Contact MTM Precision

 

MTM Precision Sdn. Bhd.

 

Showroom & Service Centre

 

No. 29-1 & 29-2, Jalan Bandar 18,

Pusat Bandar Puchong,

47160 Puchong, Selangor, Malaysia

 

🌐 Website: www.mtmpre.com.my

📧 Email: mtmpre@yahoo.com

📱 WhatsApp: +6016-660 7346

 

For Langry APT200 Anchor Pull-Out Tester Malaysia, anchor bolt testing equipment, construction testing instruments and technical product enquiries, contact MTM Precision.


 

11 Aug 2026