How to Read an Anchor Pull-Out Test Result – kN Reading, Pass or Fail Explained Malaysia

How to Read an Anchor Pull-Out Test Result – kN Reading, Pass or Fail Explained Malaysia


How Do You Interpret an Anchor Pull-Out Test Result?


An anchor pull-out tester may display a force reading such as:


45.2kN


82.5kN


120.0kN


or


150.8kN


But what does that number actually mean?


The most important point is:


A force reading by itself does not automatically tell you whether an anchor has passed or failed.


To interpret an anchor pull-out test correctly, the measured force must be compared with the approved test requirement and acceptance criteria for the project.


For professional field testing, instruments such as the Langry APT200 Anchor Pull-Out Tester can measure tensile force up to 200kN for suitable applications.


What Does kN Mean?


Anchor pull-out test force is commonly expressed in:


kN – kilonewtons


One kilonewton equals:


1,000 newtons


Kilonewtons are units of force, not mass.


This distinction is important when reading engineering test results.


Is kN the Same as kg?


No.


kN measures force.


kg measures mass.


They should not be treated as the same unit.


For approximate comparison under standard gravity:


1kN ≈ 102kgf


Therefore:


10kN ≈ 1.02 tonnes-force


100kN ≈ 10.2 tonnes-force


200kN ≈ 20.4 tonnes-force


For engineering documentation, it is generally better to retain the specified force unit, such as kN.


Example 1 – Required Load 50kN


Suppose the approved project requirement states:


Proof Load: 50kN


The tester reaches:


50.4kN


Has the anchor passed?


Possibly—but the force reading alone is not enough.


You must also check the project's other acceptance criteria.


For example:


Was the load held for the required time?


Was movement within the permitted limit?


Was there any visible failure?


Was the approved procedure followed?


Only then can the result be assessed correctly.


Example 2 – Required Load 80kN


Suppose:


Required Proof Load: 80kN


but the anchor begins to pull out at:


62kN


The anchor did not reach the required test load.


This would normally require action according to the project's approved failure procedure.


The operator should record:


Maximum achieved load


Anchor behaviour


Failure mode


Test location


Photographs


Other required observations


Example 3 – Anchor Reaches the Load but Moves Excessively


Suppose the required load is:


100kN


The tester reaches:


100kN


but the anchor experiences movement beyond an acceptance limit defined by the project.


The anchor should not automatically be marked PASS merely because the force reached 100kN.


Acceptance must consider all specified criteria.


Example 4 – 200kN Tester Used for a 60kN Test


Suppose you are using a:


Langry APT200 – Maximum Measurement Range 200kN


but the project requires:


60kN Proof Load


The relevant target remains:


60kN


Do not continue loading to 200kN simply because the tester can measure that force.


Tester Capacity Is Not the Pass Requirement


This is one of the most common misunderstandings.


If the equipment specification says:


Maximum Range: 200kN


this means the tester's measurement range extends to 200kN.


It does not mean:


Every anchor must withstand 200kN.


The test requirement comes from the project.


Where Does the Required Test Load Come From?


Depending on the project, the required load may be defined by:


Structural engineer


Façade engineer


Consultant


Approved method statement


Project specification


Approved anchor design


Applicable test procedure


The test operator should know this value before testing starts.


What Is a Proof Load?


A proof load is a specified test force applied according to an approved procedure to verify an installed anchor.


For example:


Specified Proof Load: 75kN


The operator loads the anchor according to the approved procedure up to the specified value.


The test may then require the force to be maintained for a defined period.


The anchor is assessed against the approved acceptance criteria.


What Is Maximum Applied Load?


The maximum applied load is the highest measured force reached during the test.


For example:


Required Proof Load: 75kN


Maximum Applied Load: 75.6kN


These two numbers describe different things.


The first is the requirement.


The second is the measured test result.


What Is Failure Load?


For a destructive or ultimate test, the report may record the load associated with the defined failure condition.


For example:


Maximum / Failure Load: 126.4kN


However, the force value should ideally be accompanied by a description of the observed failure mode.


Why Failure Mode Matters


Suppose two anchors both fail at approximately 120kN.


Anchor A experiences a bond-related failure.


Anchor B experiences concrete breakout.


The maximum forces may be similar, but the physical behaviour is different.


Therefore, a professional result should not consist of only:


120kN


It should also document what happened.


Common Anchor Failure Behaviours


Possible observations include:


Anchor Pull-Out


The anchoring component is extracted from the base material.


Bond-Related Failure


Failure occurs along the bonded anchorage.


Concrete Breakout


A section of concrete fails around the anchor.


Concrete Cracking or Splitting


Cracking develops around the test area.


Steel Failure


The steel component itself fails.


Connection Failure


The testing adapter or connection fails before the anchor can be properly evaluated.


These observations can be important during engineering review.


What Does “PASS” Mean?


A PASS result should mean that the anchor satisfied the defined acceptance criteria for that test.


Depending on the approved procedure, this may involve:


Required force achieved


Required holding period completed


Movement within limits


No unacceptable failure


Other specified conditions


The word PASS should not simply mean:


“The anchor did not come out.”


What Does “FAIL” Mean?


A FAIL result means the anchor did not satisfy one or more of the defined acceptance criteria.


Examples may include:


Did not reach required load


Excessive movement


Anchor pull-out


Concrete failure


Other unacceptable behaviour


The report should identify the actual reason.


Do Not Invent Pass/Fail Criteria at Site


The test operator should not decide:


“Looks strong enough, so PASS.”


Likewise, a contractor should not change the requirement after seeing the test result.


Acceptance criteria should be established before testing.


What Is Holding Time?


Some proof-test procedures require the specified load to be maintained for a defined period.


If the project specifies a holding time, the report may need to record:


Target load


Holding duration


Force behaviour


Anchor movement where required


Reaching the target force momentarily may not satisfy a procedure that requires the load to be held.


Why Anchor Movement Can Matter


Some test procedures may require displacement or movement to be monitored.


An anchor can reach the specified force while still exhibiting behaviour that requires evaluation.


Where displacement criteria apply, appropriate measurement equipment and procedures should be used.


Example Anchor Pull-Out Test Result Table


A project report might use a format such as:


Anchor IDRequired LoadMaximum Applied LoadObservationResultA0150kN50.3kNNo abnormal observationAssess per criteriaA0250kN50.5kNNo abnormal observationAssess per criteriaA0350kN38.6kNAnchor movement observedReview / Fail per criteria


The actual report format should follow the project's requirements.


Why Anchor ID Is Essential


A reading without a location is of limited value.


For example:


Test Result: 82.6kN


Which anchor?


Which floor?


Which grid?


Which bracket?


A good report connects the reading to a specific physical anchor.


Recommended Location Information


Depending on the project, record:


Tower


Block


Floor


Grid


Elevation


Zone


Bracket number


Anchor ID


This creates traceability.


Why Photographs Help Interpret Results


Photographs can provide context that a force reading cannot.


Useful photographs include:


Anchor before testing


Test setup


Tester reading


Anchor after testing


Concrete condition


Any observed failure


The photograph should be linked to the correct anchor ID.


Equipment Information Should Be Recorded


For professional testing, the report may also identify:


Manufacturer


Model


Serial number


Measurement range


Calibration information where required


This helps establish which instrument produced the measurement.


Why Calibration Matters When Reading Results


Suppose a report states:


Maximum Applied Load: 150.2kN


The usefulness of that measurement depends partly on confidence in the measurement equipment.


Depending on project requirements, calibration documentation may therefore form part of the testing records.


Langry APT200 for Force Measurement


For suitable anchor pull-out testing applications, the Langry APT200 provides:


Measurement Range: 0–200kN


approximately:


20-ton class capacity


The system also supports storage of up to 500 measurement records.


This can be useful when multiple anchors are being tested on a project.


Stored Readings Still Need Context


Suppose the instrument contains:


48.6kN


51.2kN


50.8kN


49.9kN


Without proper project records, you may not know which reading belongs to which anchor.


Therefore:


Digital Reading + Anchor ID + Location + Test Requirement + Observation


is much more useful than a force number alone.


How to Review a Pull-Out Test Report


When reviewing a report, check:


Is the project identified?


Are the test locations clear?


Are anchor IDs provided?


Is the required load stated?


Is the applied load recorded?


Is holding time recorded where required?


Is movement recorded where required?


Are observations included?


Is pass/fail based on defined criteria?


Is the equipment identified?


Is calibration information provided where required?


Are photographs traceable to test points?


If several of these are missing, clarification may be needed.


What If the Result Is Very Close to the Required Load?


Do not create your own tolerance.


For example:


Required: 100kN


Measured: 99.5kN


Whether that is acceptable depends on the approved procedure, measurement considerations and project acceptance criteria.


The operator should not simply round the number up to 100kN and declare PASS.


What If the Reading Drops During Holding?


A falling reading may require investigation depending on the test procedure and equipment behaviour.


Possible factors could include:


Anchor movement


Test setup behaviour


Hydraulic system behaviour


Connection movement


Other mechanical effects


Record what happened and assess it according to the approved procedure rather than hiding the change.


What Should Happen After a Failed Result?


A professional process may include:


Stop and secure the test


Record the maximum force


Record the observed failure behaviour


Photograph the anchor


Identify the test location


Inform the responsible project team


Follow the approved failure procedure


Perform additional testing only where instructed


Do not delete or ignore a failed reading.


Frequently Asked Questions


What does the kN reading on an anchor pull-out tester mean?


It represents the measured tensile force applied during the test.


Does reaching the specified kN automatically mean PASS?


Not necessarily. Other acceptance criteria such as holding time, movement or visible behaviour may also apply.


What does 100kN equal in tons?


100kN is approximately 10.2 metric tonnes-force.


What does 200kN equal in tons?


200kN is approximately 20.4 metric tonnes-force.


Is tester capacity the same as required test load?


No. Tester capacity is the equipment's measurement range. The required test load comes from the project requirements.


Who determines pass or fail?


Pass/fail should be assessed against the approved acceptance criteria.


Should a report include the failure mode?


Where failure occurs, documenting the observed failure behaviour provides important information.


Should the tester serial number be recorded?


For professional traceability, equipment identification can be important and may be required by the project.


Is Langry APT200 suitable for professional anchor testing?


It can be suitable for applications where the required force and test configuration fall within its 200kN measurement range.


Anchor Pull-Out Test Equipment Malaysia


MTM Precision supplies professional construction and civil engineering testing equipment for:


Contractors


QA/QC teams


Façade contractors


Structural contractors


Testing companies


Inspection laboratories


For equipment selection, send:


Anchor Type + Anchor Diameter + Required Test Load + Application


This helps determine whether the Langry APT100, APT200 or APT300 is appropriate for the required testing range.


Contact MTM Precision


MTM Precision Sdn. Bhd.


Showroom & Service Centre


No. 29-1 & 29-2, Jalan Bandar 18,

Pusat Bandar Puchong,

47160 Puchong, Selangor, Malaysia


🌐 Website: www.mtmpre.com.my

📧 Email: mtmpre@yahoo.com

📱 WhatsApp: +6016-660 7346


For Langry APT200 Anchor Pull-Out Tester Malaysia, current quotation, model selection and professional construction testing equipment enquiries, contact MTM Precision.



11 Aug 2026